1212 N CASIANO ROAD 90049

Certificate Information: 1212 N CASIANO ROAD 90049

Application / Permit
23010-30000-01006
Plan Check / Job No.
B23WL00611
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
NEW OPEN ROOF (TRELLIS) PATIO STRUCTURE.
Permit Issued
Issued on 8/30/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2023 APPLICANT
Assigned to Plan Check Engineer 3/16/2023 SERGIO SILVA
Corrections Issued 3/22/2023 SERGIO SILVA
Quality Review Completed 3/31/2023 KAVIAN REFAHI
Building Plans Picked Up 4/10/2023 APPLICANT
Applicant returned to address corrections 5/24/2023 SERGIO SILVA
Plan Check Approved 7/26/2023 SERGIO SILVA
Issued 8/30/2024 APPLICANT
CofO in Progress 10/21/2025 CARLOS MATAMOROS
Permit Finaled 10/22/2025 RICHARD STEINBACH
CofO Issued 10/22/2025 RICHARD STEINBACH
Permit Finaled 10/22/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/25/2023 DINAH GARIN
Grading Pre-Inspection Cleared 7/26/2023 SERGIO SILVA
Miscellaneous Cleared 7/26/2023 SERGIO SILVA
Miscellaneous Cleared 7/26/2023 SERGIO SILVA
Miscellaneous Cleared 7/26/2023 SERGIO SILVA
Roof/Waste drainage to street Cleared 7/26/2023 DARIN LAM

Contact Information

Contractor Jones Harold Landscape Inc; Lic. No.: 281597-B 530 E LOS ANGELES AVE   #115-356    MOORPARK, CA 93021
Engineer Amoroso,, Gregory; Lic. No.: L8771 24269 PALO VERDE DR      VALENCIA, CA 91354
Engineer Ekmekji,, Steve Eli; Lic. No.: C66727 19281 BERCLAIR LANE      TARZANA, CA 91356
Engineer Hollingsworth,, Robert Alan; Lic. No.: GE2022 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362
Geologist Hollingsworth,, Robert Alan; Lic. No.: EG1265 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/27/2025 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 6/23/2025 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 6/23/2025 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 7/9/2025 Partial Approval MEL KHACHATOURIAN
Grounding or Bonding 7/9/2025 Approved MEL KHACHATOURIAN
Structural Steel Frame 7/9/2025 Not Ready for Inspection MEL KHACHATOURIAN
Structural Steel Frame 7/11/2025 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 10/15/2025 Approved CARLOS MATAMOROS
ELECTRICAL-Final 10/15/2025 Approved CARLOS MATAMOROS
Final 10/15/2025 OK to Issue CofO CARLOS MATAMOROS
Footing/Foundation/Slab 10/15/2025 Approved CARLOS MATAMOROS
MERV13>=Final 10/15/2025 Approved CARLOS MATAMOROS
MERV13>=Rough 10/15/2025 Approved CARLOS MATAMOROS
PLUMBING-Final 10/15/2025 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 10/15/2025 SGSOV Approved CARLOS MATAMOROS
Service/Power Release 10/15/2025 Approved CARLOS MATAMOROS
Smoke Detectors 10/15/2025 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 10/15/2025 Approved CARLOS MATAMOROS