736 1/2 E BROOKS AVE 90291

Certificate Information: 736 1/2 E BROOKS AVE 90291

Application / Permit
23010-30000-00970
Plan Check / Job No.
B23WL00595
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached 3-car garage (725 sf) with ADU (708 sf) above per LAMC 12.22 A.33(c) AND (d) and per DIR-2023-2075-CDP-MEL-HCA
Permit Issued
Issued on 8/8/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/8/2023 APPLICANT
Assigned to Plan Check Engineer 3/8/2023 REZA HAGHIGHAT
Corrections Issued 3/11/2023 REZA HAGHIGHAT
Quality Review Completed 3/14/2023 KAVIAN REFAHI
Building Plans Picked Up 3/16/2023 APPLICANT
Plan Check Approved 8/5/2024 REZA HAGHIGHAT
Issued 8/8/2024 APPLICANT
CofO in Progress 8/27/2025 MICHAEL ALLEN
CofO in Progress 8/27/2025 DAVID FEILER
CofO in Progress 9/9/2025 DAVID FEILER
Permit Finaled 9/9/2025 RICHARD STEINBACH
CofO Issued 9/9/2025 RICHARD STEINBACH
Permit Finaled 9/9/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 1/30/2024 BRENDEN HAWK
Eng Process Fee Ord 176,300 Cleared 2/2/2024 BRENDEN HAWK
Sewer availability Cleared 3/6/2024 BRENDEN HAWK
Hydrant and Access approval Cleared 3/17/2024 JOHN CONNEALLY
Coastal Zone Cleared 4/12/2024 ROSALINDA MEZA
Frnt yard landscape/Water mgmt Cleared 4/12/2024 ROSALINDA MEZA
Specific Plan Cleared 4/12/2024 ROSALINDA MEZA
ZA Case Cleared 4/23/2024 ROSALINDA MEZA
ZA Case Cleared 4/23/2024 ROSALINDA MEZA
Specific Plan Cleared 5/15/2024 FREDDY GARCIA
Low Impact Development (LID) Cleared 6/7/2024 LUIS LUVANO
Roof/Waste drainage to street Cleared 6/16/2024 BRENDEN HAWK
ZA Case Cleared 7/24/2024 DANIEL CORONADO

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 19145 MALABAR ST      SANTA CLARITA, CA 91351

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/4/2024 Corrections Issued HERBERT GIRON
Sewer 11/4/2024 Approved HERBERT GIRON
Excavation/Setback/Form/Re-Bar 11/26/2024 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 11/26/2024 Corrections Issued HERBERT GIRON
Excavation/Setback/Form/Re-Bar 12/2/2024 Approved JESUS PINEDA
Footing/Foundation/Slab 12/2/2024 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 1/6/2025 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 1/13/2025 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 1/24/2025 Corrections Issued HERBERT GIRON
Special/Order Compliance 1/24/2025 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 2/3/2025 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 2/20/2025 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 2/26/2025 Conditional Approval HERBERT GIRON
ELECTRICAL-Rough 3/10/2025 Approved JESUS RODRIGUEZ
PLUMBING-Rough 3/10/2025 Approved JESUS RODRIGUEZ
HVAC-Rough 3/18/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 3/18/2025 Approved JESUS RODRIGUEZ
Special/Order Compliance 3/18/2025 Corrections Issued JESUS RODRIGUEZ
Interior/Exterior Lathing 3/24/2025 Approved JESUS RODRIGUEZ
Shower Pan 3/24/2025 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 4/2/2025 Approved JESUS RODRIGUEZ
Drywall Nailing 4/2/2025 Approved JESUS RODRIGUEZ
Green Building Rough 4/2/2025 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 4/2/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 4/7/2025 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 6/20/2025 Approved JESUS RODRIGUEZ
PLUMBING-Final 6/20/2025 Approved JESUS RODRIGUEZ
Service/Power Release 6/20/2025 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Final 6/27/2025 Corrections Issued JESUS RODRIGUEZ
Smoke Detectors 6/27/2025 Approved JESUS RODRIGUEZ
HVAC-Final 7/8/2025 Approved MICHAEL ALLEN
Final 8/26/2025 Not Ready for Inspection MICHAEL ALLEN
Green Building Final 8/26/2025 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 8/26/2025 SGSOV Approved MICHAEL ALLEN
Service/Power Release 8/26/2025 Approved MICHAEL ALLEN
Special/Order Compliance 8/27/2025 Corrections Issued MICHAEL ALLEN
Final 9/9/2025 OK to Issue CofO DAVID FEILER