10623 W OLYMPIC BLVD 90025
Certificate Information: 10623 W OLYMPIC BLVD 90025
- Application / Permit
- 23010-30000-00799
- Plan Check / Job No.
- B23WL00484
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (e) garage into a 2 story ADU over a 1 car garage. "COMPLY WITH DEPARTMENT ORDER effective date 01/24/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 3/22/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2023 | RICHARD GARCIA |
| Corrections Issued | 3/7/2023 | RICHARD GARCIA |
| Building Plans Picked Up | 3/8/2023 | APPLICANT |
| Plan Check Approved | 3/17/2023 | JAHANSHAH POURHASSAN |
| Issued | 3/22/2023 | APPLICANT |
| CofO in Progress | 12/21/2023 | ROBERT CHAVEZ |
| Permit Finaled | 1/11/2024 | DANIEL SANCHEZ |
| CofO Issued | 1/11/2024 | DANIEL SANCHEZ |
| Permit Finaled | 1/11/2024 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 3/8/2023 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2023 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 3/9/2023 | HISASHI KOBAYAKAWA |
| Low Impact Development (LID) | Cleared | 3/15/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 3/15/2023 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 3/15/2023 | EDUARDO HERMOSO |
| Grading Pre-Inspection | Cleared | 3/16/2023 | KIRK LINKLATER |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| PETER RUBIO, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN TCHANG, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| RYAN TAGUINES, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/5/2023 | Partial Approval | JOHN TCHANG |
| Footing/Foundation/Slab | 4/10/2023 | Approved | JOHN TCHANG |
| METHANE-Barrier | 4/10/2023 | Approved | JOHN TCHANG |
| METHANE-Subgrade | 4/10/2023 | Approved | JOHN TCHANG |
| BUILDING-Rough-Frame | 6/8/2023 | Partial Approval | PETER RUBIO |
| ELECTRICAL-Rough | 6/8/2023 | Not Ready for Inspection | PETER RUBIO |
| Green Building Rough | 6/8/2023 | Not Ready for Inspection | PETER RUBIO |
| HVAC-Rough | 6/8/2023 | Partial Approval | PETER RUBIO |
| METHANE-Rough | 6/8/2023 | Approved | PETER RUBIO |
| PLUMBING-Rough | 6/8/2023 | Corrections Issued | PETER RUBIO |
| PLUMBING-Rough | 6/13/2023 | Approved | JOHN TCHANG |
| ELECTRICAL-Rough | 6/20/2023 | Approved | RUBEN PEREZ |
| Insulation | 6/20/2023 | Partial Approval | RUBEN PEREZ |
| Interior/Exterior Lathing | 6/20/2023 | Partial Inspection | RUBEN PEREZ |
| Shower Pan | 6/20/2023 | Approved | RUBEN PEREZ |
| Insulation | 6/26/2023 | Approved | RUBEN PEREZ |
| Interior/Exterior Lathing | 6/26/2023 | Approved | RUBEN PEREZ |
| Drywall Nailing | 7/10/2023 | Approved | RUBEN PEREZ |
| PLUMBING-Rough | 7/18/2023 | Approved | ROBERT CHAVEZ |
| ELECTRICAL-Rough | 7/26/2023 | Approved | ROBERT CHAVEZ |
| Service/Power Release | 7/26/2023 | Approved | ROBERT CHAVEZ |
| BUILDING-Rough-Frame | 9/21/2023 | Approved | ROBERT CHAVEZ |
| Final | 9/21/2023 | Not Ready for Inspection | ROBERT CHAVEZ |
| Green Building Final | 9/21/2023 | Approved | ROBERT CHAVEZ |
| Green Building Rough | 9/21/2023 | Approved | ROBERT CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 9/21/2023 | SGSOV Not Ready | ROBERT CHAVEZ |
| Smoke Detectors | 9/21/2023 | Approved | ROBERT CHAVEZ |
| Final | 12/21/2023 | OK to Issue CofO | ROBERT CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 12/21/2023 | SGSOV Approved | ROBERT CHAVEZ |