16706 W ADDISON ST 91436
Certificate Information: 16706 W ADDISON ST 91436
- Application / Permit
- 23010-30000-00272
- Plan Check / Job No.
- B22LA26294
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPlan: New Detached 1-Story ADU per GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c),(d), and (g)
- Permit Issued
- Issued on 11/20/2023
- Issuing Office
- Current Status
- CofO Issued on 1/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2023 | DAVID CASTILLO |
| Corrections Issued | 1/26/2023 | DAVID CASTILLO |
| Quality Review Completed | 2/2/2023 | KAVIAN REFAHI |
| Plan Check Approved | 8/8/2023 | DAVID CASTILLO |
| Issued | 11/20/2023 | APPLICANT |
| CofO in Progress | 1/8/2025 | THOMAS FINNILA |
| Permit Finaled | 1/8/2025 | JOHN JANSON |
| CofO Issued | 1/8/2025 | JOHN JANSON |
| Permit Finaled | 1/8/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/14/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2023 | MEGAN GODINEZ |
| Hydrant and Access approval | Cleared | 4/26/2023 | KURT CORRAL |
| Sewer availability | Cleared | 4/26/2023 | MEGAN GODINEZ |
| Construction near power lines | Cleared | 5/25/2023 | RIDWAN HARDY |
| Low Impact Development | Cleared | 6/30/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 6/30/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/19/2023 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 12/19/2023 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 12/19/2023 | Partial Approval | VINCENT HANLEY |
| Footing/Foundation/Slab | 1/10/2024 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2024 | Partial Approval | VINCENT HANLEY |
| HVAC-Rough | 3/20/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 4/11/2024 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2024 | Approved | VINCENT HANLEY |
| Gas Test | 4/11/2024 | Approved | VINCENT HANLEY |
| HVAC-Rough | 4/11/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 4/11/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 4/24/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 4/24/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 4/24/2024 | Partial Approval | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 4/24/2024 | Approved | VINCENT HANLEY |
| Insulation | 5/6/2024 | Approved | VINCENT HANLEY |
| Shower Pan | 5/6/2024 | Approved | VINCENT HANLEY |
| Drywall Nailing | 5/13/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Drywall Nailing | 5/16/2024 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 5/31/2024 | Partial Approval | ARUTYUN MADATYAN |
| Underground Mechanical | 8/19/2024 | Partial Approval | THOMAS FINNILA |
| Underground Mechanical | 8/21/2024 | Partial Approval | THOMAS FINNILA |
| Gas Test | 8/26/2024 | Partial Approval | THOMAS FINNILA |
| Underground Mechanical | 8/26/2024 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 10/21/2024 | Approved | THOMAS FINNILA |
| HVAC-Final | 10/21/2024 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 11/25/2024 | Approved | THOMAS FINNILA |
| Final | 12/18/2024 | Partial Inspection | THOMAS FINNILA |
| Green Building Final | 12/18/2024 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 12/18/2024 | SGSOV Approved | THOMAS FINNILA |
| Service/Power Release | 12/18/2024 | Not Required | THOMAS FINNILA |
| Smoke Detectors | 12/18/2024 | Approved | THOMAS FINNILA |
| Final | 1/8/2025 | OK to Issue CofO | THOMAS FINNILA |