2363 S KELTON AVE 90064
Certificate Information: 2363 S KELTON AVE 90064
- Application / Permit
- 23010-30000-00018
- Plan Check / Job No.
- B23WL00026
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New Detached 1-Story ADU per GCS 65852.2(e)(1)(B) and LAMC 12.22A.33(c),(d), and (g)
- Permit Issued
- Issued on 9/19/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2023 | DAVID CASTILLO |
| Corrections Issued | 1/24/2023 | DAVID CASTILLO |
| Applicant returned to address corrections | 8/15/2023 | DAVID CASTILLO |
| Plan Check Approved | 9/8/2023 | MICHAEL LANZONE |
| Issued | 9/19/2023 | APPLICANT |
| CofO in Progress | 2/21/2025 | ARAM AVEDISIAN |
| Permit Finaled | 2/26/2025 | RICHARD STEINBACH |
| CofO Issued | 2/26/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/26/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 3/2/2023 | JENSON LEE |
| Construction near power lines | Cleared | 7/28/2023 | TINA MIRANDA |
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2023 | DARIN LAM |
| Sewer availability | Cleared | 7/31/2023 | DARIN LAM |
| Specific Plan | Cleared | 7/31/2023 | PEDRO AYALA |
| Roof/Waste drainage to street | Cleared | 8/3/2023 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 9/8/2023 | MICHAEL LANZONE |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Owner-Builder | , |
| Engineer | Namdar,, Mansour; Lic. No.: S2976 | 16867 SEVERO PLACE ENCINO, CA 91436 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/25/2023 | Corrections Issued | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 12/12/2023 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 12/12/2023 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 12/12/2023 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 12/18/2023 | Partial Approval | JESUS PINEDA |
| Underground Mechanical | 12/18/2023 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 1/31/2024 | Partial Approval | JESUS PINEDA |
| Sewer | 1/31/2024 | Approved | JESUS PINEDA |
| Footing/Foundation/Slab | 3/6/2024 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2024 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2024 | Partial Approval | JESUS PINEDA |
| BUILDING-Rough-Frame | 6/3/2024 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2024 | Approved | JESUS PINEDA |
| HVAC-Rough | 6/11/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 6/11/2024 | Corrections Issued | JESUS PINEDA |
| Shower Pan | 6/11/2024 | Corrections Issued | JESUS PINEDA |
| Interior/Exterior Lathing | 6/13/2024 | Partial Approval | JESUS PINEDA |
| Shower Pan | 6/13/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 7/1/2024 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 7/1/2024 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 7/3/2024 | Approved | MEL KHACHATOURIAN |
| Wood Frame | 7/3/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 7/8/2024 | Conditional Approval | KIRK SANDERS |
| Special/Order Compliance | 7/8/2024 | Corrections Issued | KIRK SANDERS |
| Verify Sprinkler Sign Off | 7/8/2024 | Approved | KIRK SANDERS |
| Insulation | 7/19/2024 | Corrections Issued | JESUS PINEDA |
| Drywall Nailing | 7/31/2024 | Not Ready for Inspection | JESUS PINEDA |
| Green Building Rough | 7/31/2024 | Approved | JESUS PINEDA |
| Insulation | 7/31/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 7/31/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 10/18/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Final | 10/22/2024 | Approved | DANIEL VERA |
| ELECTRICAL-Final | 10/23/2024 | Approved | DANIEL VERA |
| ELECTRICAL-Final | 10/30/2024 | Approved | DANIEL VERA |
| PLUMBING-Final | 10/30/2024 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 11/25/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 11/25/2024 | Approved | BOBBY KEY |
| Final | 11/25/2024 | Corrections Issued | BOBBY KEY |
| Green Building Final | 11/25/2024 | Approved | BOBBY KEY |
| HVAC-Final | 11/25/2024 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 11/25/2024 | SGSOV Not Required | BOBBY KEY |
| Service/Power Release | 11/25/2024 | Not Ready for Inspection | BOBBY KEY |
| Smoke Detectors | 11/25/2024 | Approved | BOBBY KEY |
| Final | 12/9/2024 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 12/9/2024 | Approved | TEMISTOCLES CAAL |
| Service/Power Release | 12/9/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Final | 12/12/2024 | Not Ready for Inspection | DANIEL VERA |
| Service/Power Release | 12/12/2024 | Approved | DANIEL VERA |
| Final | 2/21/2025 | OK to Issue CofO | ARAM AVEDISIAN |