15231 W SHERMAN WAY 91405
Certificate Information: 15231 W SHERMAN WAY 91405
- Application / Permit
- 23010-20001-04944
- Plan Check / Job No.
- B25VN06285
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- <ePLAN> SUPPLEMENTAL PERMIT TO 23010-20000-04944 TO REVISE DESIGN TO MAKE THE 2 ADUS A 26'0"X46'3" 2-STORY BUILDING BY ADDING THE A GARAGE ON THE 1ST FLOOR (NFPA-13R FIRE SPRINKLERS REQUIRED THROUHGOUT)
- Permit Issued
- Issued on 7/24/2025
- Issuing Office
- Current Status
- Issued on 7/24/2025
Permit Application Status History
| Submitted | 3/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2025 | MARVEL DELACRUZ |
| Corrections Issued | 3/25/2025 | MARVEL DELACRUZ |
| Quality Review Completed | 4/1/2025 | JASON HEALEY |
| Applicant returned to address corrections | 4/24/2025 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 5/6/2025 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 5/22/2025 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 6/2/2025 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 6/16/2025 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 6/26/2025 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 7/3/2025 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 7/14/2025 | MARVEL DELACRUZ |
| Plan Check Approved | 7/22/2025 | MARVEL DELACRUZ |
| Issued | 7/24/2025 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | New Beginning Construction Company Corp The; Lic. No.: 848904-B | , |
| Contractor | New Beginnning Construction Company The; Lic. No.: 848904-B | , |
| Engineer | Castillo,, Margarito; Lic. No.: NA4808 | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/5/2025 | Corrections Issued | VINCENT HANLEY |
| Pre-Inspection | 8/5/2025 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 8/11/2025 | Approved | VINCENT HANLEY |
| Structural Steel Frame | 8/11/2025 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2025 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 12/10/2025 | Corrections Issued | MATTHEW NELSON |
| HVAC-Rough | 12/10/2025 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 12/10/2025 | Corrections Issued | MATTHEW NELSON |
| Wood Frame | 12/10/2025 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 1/8/2026 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 1/8/2026 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2026 | Approved | VINCENT HANLEY |
| Green Building Rough | 1/8/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 1/8/2026 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 1/8/2026 | Approved | VINCENT HANLEY |
| Insulation | 1/26/2026 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 1/26/2026 | Partial Approval | VINCENT HANLEY |
| Drywall Nailing | 2/2/2026 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 2/2/2026 | Approved | VINCENT HANLEY |