15231 W SHERMAN WAY 91405

Certificate Information: 15231 W SHERMAN WAY 91405

Application / Permit
23010-20001-04944
Plan Check / Job No.
B25VN06285
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
<ePLAN> SUPPLEMENTAL PERMIT TO 23010-20000-04944 TO REVISE DESIGN TO MAKE THE 2 ADUS A 26'0"X46'3" 2-STORY BUILDING BY ADDING THE A GARAGE ON THE 1ST FLOOR (NFPA-13R FIRE SPRINKLERS REQUIRED THROUHGOUT)
Permit Issued
Issued on 7/24/2025
Issuing Office
Current Status
Issued on 7/24/2025

Permit Application Status History

Submitted 3/10/2025 APPLICANT
Assigned to Plan Check Engineer 3/20/2025 MARVEL DELACRUZ
Corrections Issued 3/25/2025 MARVEL DELACRUZ
Quality Review Completed 4/1/2025 JASON HEALEY
Applicant returned to address corrections 4/24/2025 MARVEL DELACRUZ
Applicant returned to address corrections 5/6/2025 MARVEL DELACRUZ
Applicant returned to address corrections 5/22/2025 MARVEL DELACRUZ
Applicant returned to address corrections 6/2/2025 MARVEL DELACRUZ
Applicant returned to address corrections 6/16/2025 MARVEL DELACRUZ
Applicant returned to address corrections 6/26/2025 MARVEL DELACRUZ
Applicant returned to address corrections 7/3/2025 MARVEL DELACRUZ
Applicant returned to address corrections 7/14/2025 MARVEL DELACRUZ
Plan Check Approved 7/22/2025 MARVEL DELACRUZ
Issued 7/24/2025 APPLICANT

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor New Beginning Construction Company Corp The; Lic. No.: 848904-B       ,
Contractor New Beginnning Construction Company The; Lic. No.: 848904-B       ,
Engineer Castillo,, Margarito; Lic. No.: NA4808       ,
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/5/2025 Corrections Issued VINCENT HANLEY
Pre-Inspection 8/5/2025 Approved VINCENT HANLEY
Footing/Foundation/Slab 8/11/2025 Approved VINCENT HANLEY
Structural Steel Frame 8/11/2025 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 8/29/2025 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 12/10/2025 Corrections Issued MATTHEW NELSON
HVAC-Rough 12/10/2025 Approved MATTHEW NELSON
PLUMBING-Rough 12/10/2025 Corrections Issued MATTHEW NELSON
Wood Frame 12/10/2025 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 1/8/2026 Approved VINCENT HANLEY
ELECTRICAL-Rough 1/8/2026 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 1/8/2026 Approved VINCENT HANLEY
Green Building Rough 1/8/2026 Approved VINCENT HANLEY
PLUMBING-Rough 1/8/2026 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 1/8/2026 Approved VINCENT HANLEY
Insulation 1/26/2026 Approved VINCENT HANLEY
Interior/Exterior Lathing 1/26/2026 Partial Approval VINCENT HANLEY
Drywall Nailing 2/2/2026 Approved VINCENT HANLEY