8943 N KESTER AVE 91402
Certificate Information: 8943 N KESTER AVE 91402
- Application / Permit
- 23010-20001-03407
- Plan Check / Job No.
- B24VN26286
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: SUPPLEMENTAL TO PERMIT 23010-20000-03407 TO CHANGE THE WORK DESCRIPTION TO "(N) 1-STORY ACCESSORY DWELLING UNIT CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g). FIRE SPRINKLER 13D THROUGH OUT."
- Permit Issued
- Issued on 4/29/2025
- Issuing Office
- Current Status
- Issued on 4/29/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2025 | DANIEL YIP |
| Corrections Issued | 1/3/2025 | DANIEL YIP |
| Quality Review Completed | 1/10/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 4/11/2025 | DANIEL YIP |
| Plan Check Approved | 4/28/2025 | DANIEL YIP |
| Issued | 4/29/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/23/2025 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2025 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 3/18/2025 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 3/19/2025 | CARLOS AGUILERA |
| Private sewage disp. approval | Cleared | 4/21/2025 | DAN RYAN EVANGELISTA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/25/2026 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 3/6/2026 | Partial Approval | OGANES TARAKHCHYAN |
| Pre-Inspection | 3/6/2026 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Underground Mechanical | 3/6/2026 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 3/12/2026 | Approved | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 3/12/2026 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2026 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 4/20/2026 | Conditional Approval | GAREN HAYRAPETYAN |
| HVAC-Rough | 4/20/2026 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 4/20/2026 | Approved | GAREN HAYRAPETYAN |
| Special/Order Compliance | 4/20/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 5/8/2026 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 5/8/2026 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 5/8/2026 | Partial Approval | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 5/8/2026 | Approved | OGANES TARAKHCHYAN |
| Insulation | 5/29/2026 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 6/24/2026 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 6/30/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 7/13/2026 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 7/13/2026 | Approved | JAVIER RAMOS JR |