343-343 1/2 W 46TH ST 90037
Certificate Information: 343-343 1/2 W 46TH ST 90037
- Application / Permit
- 23010-20001-00074
- Plan Check / Job No.
- B24VN02169
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPLEMENTAL TO 23010-20000-00074 TO REVISE ARCHITECTURAL AND STRUCTURAL PLANS AND CHANGE THE GARAGE TO ADU
- Permit Issued
- Issued on 4/5/2024
- Issuing Office
- Current Status
- Permit Finaled on 8/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2024 | ARSALAN SHABESTARI |
| Corrections Issued | 3/13/2024 | ARSALAN SHABESTARI |
| Plan Check Approved | 4/4/2024 | ARSALAN SHABESTARI |
| Issued | 4/5/2024 | APPLICANT |
| Permit Finaled | 8/4/2025 | ALEJANDRO DE ARTOLA |
Permit Application Clearance Information
| Address approval | Cleared | 3/19/2024 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/19/2024 | JEANIE LAM |
| Sewer availability | Cleared | 3/19/2024 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/17/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 5/23/2024 | Approved | JOSE MACIAS |
| Underground Mechanical | 5/23/2024 | Approved | JOSE MACIAS |
| Footing/Foundation/Slab | 7/3/2024 | Approved | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2024 | Corrections Issued | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2024 | Partial Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 10/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/29/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| HVAC-Rough | 10/29/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| ELECTRICAL-Rough | 10/30/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/31/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 11/8/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 11/8/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| MERV13>=Rough | 11/8/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 11/12/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2024 | Approved | SABAS ALONSO |
| HVAC-Rough | 11/21/2024 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 11/25/2024 | Corrections Issued | SABAS ALONSO |
| Insulation | 12/2/2024 | Not Ready for Inspection | JOSH MEISTER |
| BUILDING-Rough-Frame | 12/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 12/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Wood Frame | 12/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 12/9/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 12/9/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 12/11/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 12/11/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 1/15/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 4/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 4/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 4/30/2025 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 4/30/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 4/30/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 4/30/2025 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 5/1/2025 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 5/1/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 5/1/2025 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 6/30/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/4/2025 | Permit Finaled | ALEJANDRO DE ARTOLA |
| MERV13>=Final | 8/4/2025 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 8/4/2025 | Approved | ALEJANDRO DE ARTOLA |