18200 W SHEFFIELD LANE 91326
Certificate Information: 18200 W SHEFFIELD LANE 91326
- Application / Permit
- 23010-20000-05317
- Plan Check / Job No.
- B23VN17918
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan NEW 67'6" X 75' IRREGULAR SHAPED TWO STORY SFD WITH AN ATTACHED 2 CAR GARAGE , NFPA 13R SPRINKLERS THROUGHOUT, ALL WORK PER ENGINEERING - SEE COMMENTS
- Permit Issued
- Issued on 10/30/2024
- Issuing Office
- Current Status
- CofO Issued on 8/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2024 | RARES BODEA |
| Corrections Issued | 2/2/2024 | RARES BODEA |
| Quality Review Completed | 2/9/2024 | STEVEN KIM |
| Applicant returned to address corrections | 10/8/2024 | RARES BODEA |
| Applicant returned to address corrections | 10/16/2024 | RARES BODEA |
| Applicant returned to address corrections | 10/29/2024 | RARES BODEA |
| Plan Check Approved | 10/30/2024 | RARES BODEA |
| Issued | 10/30/2024 | APPLICANT |
| CofO in Progress | 8/1/2025 | STEVEN BACK |
| Permit Finaled | 8/12/2025 | JOHN JANSON |
| CofO Issued | 8/12/2025 | JOHN JANSON |
| Permit Finaled | 8/12/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/6/2024 | EDGAR ALCARAZ |
| BHO/Hillside ordinance | Cleared | 2/6/2024 | EDGAR ALCARAZ |
| BHO/Hillside ordinance | Cleared | 2/6/2024 | EDGAR ALCARAZ |
| BHO/Hillside ordinance | Cleared | 2/6/2024 | EDGAR ALCARAZ |
| BHO/Hillside ordinance | Cleared | 2/6/2024 | EDGAR ALCARAZ |
| BHO/Hillside ordinance | Cleared | 2/6/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 2/6/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2024 | EDGAR ALCARAZ |
| Tract Map conditions | Cleared | 3/11/2024 | RUBEN VASQUEZ |
| Tract Map conditions | Cleared | 3/11/2024 | RUBEN VASQUEZ |
| Distance to fire station | Cleared | 5/9/2024 | KURT CORRAL |
| Hydrant and Access approval | Cleared | 5/9/2024 | KURT CORRAL |
| Low Impact Development | Cleared | 5/15/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 5/15/2024 | EDGAR ALCARAZ |
| Trees in Parkway | Cleared | 5/30/2024 | ADALBERTO VERA |
| Permit | Cleared | 6/3/2024 | EDGAR ALCARAZ |
| GPI Written Notices | Cleared | 10/8/2024 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 10/8/2024 | RARES BODEA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/18/2024 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 11/18/2024 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 11/25/2024 | Not Ready for Inspection | JEFFREY PARD |
| METHANE-Subgrade | 11/25/2024 | Approved | JEFFREY PARD |
| Deputy Drilled-In Anchors | 12/2/2024 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 12/2/2024 | Approved | STEVEN BACK |
| Pre-Inspection | 12/2/2024 | Partial Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 12/11/2024 | Partial Approval | JEFFREY HARTLINE |
| PLUMBING-Rough | 12/11/2024 | Partial Approval | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2024 | Approved | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2024 | Not Ready for Inspection | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2024 | Not Ready for Inspection | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 12/24/2024 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 12/26/2024 | No Access for Inspection | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2025 | No Access for Inspection | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2025 | Partial Approval | SCOTT SOBEL |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2025 | Partial Approval | STEVEN BACK |
| Special/Order Compliance | 1/31/2025 | Partial Approval | SCOTT SOBEL |
| PLUMBING-Rough | 2/6/2025 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2025 | Approved | STEVEN BACK |
| HVAC-Rough | 2/13/2025 | Corrections Issued | STEVEN BACK |
| Shower Pan | 2/13/2025 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2025 | No Access for Inspection | STEVEN BACK |
| HVAC-Rough | 2/14/2025 | No Access for Inspection | STEVEN BACK |
| Shower Pan | 2/14/2025 | No Access for Inspection | STEVEN BACK |
| Sewer | 2/19/2025 | Approved | SCOTT SOBEL |
| Underground Mechanical | 2/19/2025 | Approved | SCOTT SOBEL |
| BUILDING-Rough-Frame | 2/25/2025 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 2/25/2025 | Approved | STEVEN BACK |
| Green Building Rough | 2/25/2025 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 2/25/2025 | Approved | STEVEN BACK |
| Verify Sprinkler Sign Off | 2/25/2025 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 3/3/2025 | Approved | STEVEN BACK |
| Green Building Rough | 3/3/2025 | Approved | STEVEN BACK |
| Insulation | 3/3/2025 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 3/3/2025 | Partial Approval | STEVEN BACK |
| Insulation | 3/5/2025 | No Access for Inspection | STEVEN BACK |
| Special/Order Compliance | 3/5/2025 | Corrections Issued | STEVEN BACK |
| Insulation | 3/7/2025 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 3/7/2025 | Approved | STEVEN BACK |
| Drywall Nailing | 3/11/2025 | Not Ready for Inspection | SCOTT SOBEL |
| Drywall Nailing | 3/13/2025 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 4/7/2025 | Approved | STEVEN BACK |
| Service/Power Release | 4/7/2025 | Not Ready for Inspection | STEVEN BACK |
| Service/Power Release | 4/9/2025 | Approved | STEVEN BACK |
| PLUMBING-Rough | 5/14/2025 | Approved | STEVEN BACK |
| Final | 7/17/2025 | Not Ready for Inspection | STEVEN BACK |
| Green Building Final | 7/17/2025 | Not Ready for Inspection | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 7/17/2025 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 7/17/2025 | Not Ready for Inspection | STEVEN BACK |
| Gas Test | 7/23/2025 | Partial Approval | STEVEN BACK |
| Final | 7/25/2025 | Corrections Issued | STEVEN BACK |
| Green Building Final | 7/25/2025 | Not Ready for Inspection | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 7/25/2025 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 7/25/2025 | Approved | STEVEN BACK |
| Final | 8/1/2025 | OK to Issue CofO | STEVEN BACK |
| Green Building Final | 8/1/2025 | Approved | STEVEN BACK |
| METHANE-Final | 8/11/2025 | Approved | STEVEN BACK |