10550 N ETON AVE 91311
Certificate Information: 10550 N ETON AVE 91311
- Application / Permit
- 23010-20000-05298
- Plan Check / Job No.
- B23VN17885
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) TWO STORY 25' X 20' ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 4/23/2024
- Issuing Office
- Current Status
- CofO Issued on 8/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2024 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 1/26/2024 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 1/26/2024 | STEVEN KIM |
| Building Plans Picked Up | 1/26/2024 | APPLICANT |
| Plan Check Approved | 4/23/2024 | SEWADA ZADOORAN MILAGARDI |
| Plan Check Approved | 4/23/2024 | SEWADA ZADOORAN MILAGARDI |
| Issued | 4/23/2024 | APPLICANT |
| CofO in Progress | 8/4/2025 | DAVID SCANTLIN |
| Permit Finaled | 8/27/2025 | JOHN JANSON |
| CofO Issued | 8/27/2025 | JOHN JANSON |
| Permit Finaled | 8/27/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/30/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/30/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/30/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 1/30/2024 | LEE GUILBEAUX |
| GPI Written Notices | Cleared | 4/15/2024 | SEWADA ZADOORAN MILAGARDI |
| Grading Pre-Inspection | Cleared | 4/15/2024 | SEWADA ZADOORAN MILAGARDI |
| Roof/Waste drainage to street | Cleared | 4/18/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/25/2024 | Partial Approval | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 5/2/2024 | Approved | DAVID SCANTLIN |
| Sewer | 5/13/2024 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2024 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 6/5/2024 | Partial Approval | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 9/11/2024 | Corrections Issued | DAVID SCANTLIN |
| ELECTRICAL-Rough | 9/11/2024 | Approved | DAVID SCANTLIN |
| Green Building Rough | 9/11/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| HVAC-Rough | 9/11/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Rough | 9/11/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 9/11/2024 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 9/20/2024 | Approved | DAVID SCANTLIN |
| Green Building Rough | 9/20/2024 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 9/20/2024 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 9/20/2024 | Approved | DAVID SCANTLIN |
| Insulation | 9/30/2024 | Approved | DAVID SCANTLIN |
| Shower Pan | 9/30/2024 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 10/8/2024 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 1/29/2025 | Approved | DAVID SCANTLIN |
| Final | 1/29/2025 | Corrections Issued | DAVID SCANTLIN |
| Footing/Foundation/Slab | 1/29/2025 | Approved | DAVID SCANTLIN |
| Green Building Final | 1/29/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| HVAC-Final | 1/29/2025 | Approved | DAVID SCANTLIN |
| PLUMBING-Final | 1/29/2025 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 1/29/2025 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 1/29/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Smoke Detectors | 1/29/2025 | Approved | DAVID SCANTLIN |
| Final | 2/20/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Final | 2/20/2025 | Approved | DAVID SCANTLIN |
| Service/Power Release | 2/20/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 8/1/2025 | OK to Issue CofO | DAVID SCANTLIN |
| Service/Power Release | 8/1/2025 | Approved | DAVID SCANTLIN |