329-329 1/2 E 60TH ST 90003
Certificate Information: 329-329 1/2 E 60TH ST 90003
- Application / Permit
- 23010-20000-05280
- Plan Check / Job No.
- B23VN17861
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan: (N) 2-STORY DUPLEX WITH ATTACHED GARAGE
- Permit Issued
- Issued on 5/15/2024
- Issuing Office
- Current Status
- CofO Issued on 11/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/4/2024 | DANIEL YIP |
| Corrections Issued | 1/7/2024 | DANIEL YIP |
| Quality Review Completed | 1/8/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 4/23/2024 | DANIEL YIP |
| Plan Check Approved | 5/7/2024 | DANIEL YIP |
| Plan Check Approved | 5/14/2024 | DANIEL YIP |
| Issued | 5/15/2024 | APPLICANT |
| CofO in Progress | 11/1/2024 | ALEJANDRO DE ARTOLA |
| CofO Issued | 11/1/2024 | DEROLD HAUFF |
| Permit Finaled | 11/1/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/19/2024 | DAVID VO |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2024 | DAVID VO |
| Hydrant and Access approval | Cleared | 2/9/2024 | LAVEON RIDER |
| Sewer availability | Cleared | 2/22/2024 | JUSTIN BICOL |
| Low Impact Development (LID) | Cleared | 3/21/2024 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 4/2/2024 | JUSTIN BICOL |
| SB8 RUD | Cleared | 4/3/2024 | KEVIN SCHULTZ |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/13/2024 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 6/21/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 6/21/2024 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 6/24/2024 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 8/6/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/6/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/7/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 8/7/2024 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 8/7/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 8/7/2024 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 8/7/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/8/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 8/8/2024 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 8/22/2024 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 8/22/2024 | Approved | ALEX COLIN |
| ELECTRICAL-Final | 10/3/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 10/8/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 10/30/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 10/30/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 10/30/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/30/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 10/30/2024 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 10/30/2024 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Service/Power Release | 10/30/2024 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 10/30/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 10/31/2024 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/31/2024 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 10/31/2024 | Approved | ALEJANDRO DE ARTOLA |