17146 W STARE ST 91325

Certificate Information: 17146 W STARE ST 91325

Application / Permit
23010-20000-05279
Plan Check / Job No.
B23VN17860
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. New 1-story detached ADU at rear of the lot per LAMC 12.22 A.33(c)-(d)
Permit Issued
Issued on 5/13/2024
Issuing Office
Current Status
CofO Issued on 4/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2023 APPLICANT
Assigned to Plan Check Engineer 1/4/2024 JOHNPAUL ISIP
Corrections Issued 1/5/2024 JOHNPAUL ISIP
Applicant returned to address corrections 5/9/2024 REZA HAGHIGHAT
Plan Check Approved 5/12/2024 REZA HAGHIGHAT
Issued 5/13/2024 APPLICANT
CofO in Progress 3/14/2025 JAVIER RAMOS JR
Permit Finaled 4/10/2025 RUBEN SALAS
CofO Issued 4/10/2025 RUBEN SALAS
Permit Finaled 4/10/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/9/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/10/2024 CARLOS AGUILERA
Sewer availability Cleared 1/10/2024 CARLOS AGUILERA
Low Impact Development (LID) Cleared 2/8/2024 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 2/12/2024 CARLOS RAMIREZ
Grading Pre-Inspection Cleared 4/11/2024 CHARLES POWELL
Construction near power lines Cleared 4/24/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Karapetian,, Arbi; Lic. No.: C79953 6854 FOOTHILL BLVD      TUJUNGA, CA 91042

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/27/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 6/27/2024 Partial Approval JAVIER RAMOS JR
Pre-Inspection 6/27/2024 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 7/5/2024 Approved RAUL OLAGI
BUILDING-Rough-Frame 8/23/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 8/23/2024 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 8/23/2024 Approved JENNIFER RABUCHIN
Green Building Rough 8/23/2024 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 8/23/2024 Approved JENNIFER RABUCHIN
PLUMBING-Rough 8/23/2024 Approved JENNIFER RABUCHIN
Sewer 8/23/2024 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 8/23/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 9/4/2024 Corrections Issued MATTHEW NELSON
Green Building Rough 9/4/2024 Approved MATTHEW NELSON
Deputy Wood Construction 9/5/2024 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 9/13/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 9/13/2024 Partial Approval JAVIER RAMOS JR
Insulation 9/26/2024 Approved LOUIS ESCOTO
Drywall Nailing 10/4/2024 Approved LOUIS ESCOTO
Shower Pan 10/4/2024 Approved LOUIS ESCOTO
Interior/Exterior Lathing 11/7/2024 Approved KEVIN BERBERYAN
ELECTRICAL-Final 3/7/2025 Approved JAVIER RAMOS JR
Final 3/7/2025 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 3/7/2025 Approved JAVIER RAMOS JR
HVAC-Final 3/7/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 3/7/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 3/7/2025 SGSOV Not Required JAVIER RAMOS JR
Smoke Detectors 3/7/2025 Approved JAVIER RAMOS JR