17146 W STARE ST 91325
Certificate Information: 17146 W STARE ST 91325
- Application / Permit
- 23010-20000-05279
- Plan Check / Job No.
- B23VN17860
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. New 1-story detached ADU at rear of the lot per LAMC 12.22 A.33(c)-(d)
- Permit Issued
- Issued on 5/13/2024
- Issuing Office
- Current Status
- CofO Issued on 4/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/4/2024 | JOHNPAUL ISIP |
| Corrections Issued | 1/5/2024 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 5/9/2024 | REZA HAGHIGHAT |
| Plan Check Approved | 5/12/2024 | REZA HAGHIGHAT |
| Issued | 5/13/2024 | APPLICANT |
| CofO in Progress | 3/14/2025 | JAVIER RAMOS JR |
| Permit Finaled | 4/10/2025 | RUBEN SALAS |
| CofO Issued | 4/10/2025 | RUBEN SALAS |
| Permit Finaled | 4/10/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/9/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/10/2024 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 2/8/2024 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 2/12/2024 | CARLOS RAMIREZ |
| Grading Pre-Inspection | Cleared | 4/11/2024 | CHARLES POWELL |
| Construction near power lines | Cleared | 4/24/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Karapetian,, Arbi; Lic. No.: C79953 | 6854 FOOTHILL BLVD TUJUNGA, CA 91042 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/27/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 6/27/2024 | Partial Approval | JAVIER RAMOS JR |
| Pre-Inspection | 6/27/2024 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 7/5/2024 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 8/23/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 8/23/2024 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2024 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 8/23/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 8/23/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/23/2024 | Approved | JENNIFER RABUCHIN |
| Sewer | 8/23/2024 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 8/23/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/4/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 9/4/2024 | Approved | MATTHEW NELSON |
| Deputy Wood Construction | 9/5/2024 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 9/13/2024 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 9/13/2024 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 9/26/2024 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 10/4/2024 | Approved | LOUIS ESCOTO |
| Shower Pan | 10/4/2024 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 11/7/2024 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 3/7/2025 | Approved | JAVIER RAMOS JR |
| Final | 3/7/2025 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 3/7/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 3/7/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 3/7/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 3/7/2025 | SGSOV Not Required | JAVIER RAMOS JR |
| Smoke Detectors | 3/7/2025 | Approved | JAVIER RAMOS JR |