11025-11025 1/2 W BLIX ST 91602
Certificate Information: 11025-11025 1/2 W BLIX ST 91602
- Application / Permit
- 23010-20000-05273
- Plan Check / Job No.
- B23VN17840
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan NEW 51'9" x 33' Two-story DUPLEX PER SB9, NFPA-13D FIRE SPRINKLRES REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 7/25/2024
- Issuing Office
- Current Status
- CofO Issued on 8/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/4/2024 | RARES BODEA |
| Corrections Issued | 1/11/2024 | RARES BODEA |
| Quality Review Completed | 1/17/2024 | STEVEN KIM |
| Applicant returned to address corrections | 4/16/2024 | RARES BODEA |
| Plan Check Approved | 7/9/2024 | RARES BODEA |
| Issued | 7/25/2024 | APPLICANT |
| CofO in Progress | 7/16/2025 | JAVIER RAMOS JR |
| Permit Finaled | 8/5/2025 | RUBEN SALAS |
| CofO Issued | 8/5/2025 | RUBEN SALAS |
| Permit Finaled | 8/5/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/17/2024 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2024 | NIKKI ZULUETA |
| Sewer availability | Cleared | 1/24/2024 | NIKKI ZULUETA |
| Hydrant and Access approval | Cleared | 5/17/2024 | KURT CORRAL |
| Senate Bill 9 | Cleared | 5/21/2024 | SPENCER WEJROWSKI |
| Low Impact Development (LID) | Cleared | 6/10/2024 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 6/11/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gharai,, Armin; Lic. No.: C61464 | 6701 CORIE LN WEST HILLS, CA 91307 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/19/2024 | Approved | CHRISTOPHER ROJAS |
| Underground Mechanical | 8/30/2024 | Approved | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 9/5/2024 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Deputy Wood Construction | 9/25/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Gas Test | 9/26/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Deputy Wood Construction | 10/28/2024 | Conditional Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 11/4/2024 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 11/14/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 11/14/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 11/21/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 11/21/2024 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 12/9/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 12/19/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 12/23/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 12/23/2024 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 12/23/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 12/31/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 1/7/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Drywall Nailing | 1/14/2025 | Approved | ROBERT GOLD |
| PLUMBING-Rough | 1/14/2025 | Partial Approval | ROBERT GOLD |
| Interior/Exterior Lathing | 2/19/2025 | Partial Approval | JUAN VALENZUELA |
| Interior/Exterior Lathing | 2/28/2025 | Partial Approval | MICHAEL CORTEZ |
| Underground Mechanical | 4/30/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 6/17/2025 | Corrections Issued | JAVIER RAMOS JR |
| Final | 6/17/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 6/17/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 6/17/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 6/17/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 6/17/2025 | SGSOV Not Required | JAVIER RAMOS JR |
| Service/Power Release | 6/17/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| Smoke Detectors | 6/17/2025 | Approved | JAVIER RAMOS JR |
| Final | 7/3/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Service/Power Release | 7/3/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 7/16/2025 | Approved | JAVIER RAMOS JR |
| Final | 7/16/2025 | OK to Issue CofO | JAVIER RAMOS JR |
| Service/Power Release | 7/16/2025 | Approved | JAVIER RAMOS JR |