6831 N RANCHITO AVE 91405

Certificate Information: 6831 N RANCHITO AVE 91405

Application / Permit
23010-20000-05237
Plan Check / Job No.
B23VN17744
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 42' x 20' one story ADU per CA Govt. Code 65852.2(e)(1)(D) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g). NFPA 13D sprinkler required. All work done per WFPP.
Permit Issued
Issued on 3/13/2024
Issuing Office
Current Status
CofO Issued on 5/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2023 APPLICANT
Assigned to Plan Check Engineer 1/19/2024 NAREG ATARIAN
Corrections Issued 1/20/2024 NAREG ATARIAN
Quality Review Completed 1/24/2024 OMID HEDAYAT
Applicant returned to address corrections 3/11/2024 NAREG ATARIAN
Plan Check Approved 3/13/2024 NAREG ATARIAN
Issued 3/13/2024 APPLICANT
CofO in Progress 4/28/2025 RYAN SALAZAR
Permit Finaled 5/6/2025 RUBEN SALAS
CofO Issued 5/6/2025 RUBEN SALAS
Permit Finaled 5/6/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/23/2024 COLIN LOREDO
Low Impact Development (LID) Cleared 1/23/2024 ERNEST TSE
Eng Process Fee Ord 176,300 Cleared 1/24/2024 COLIN LOREDO
Roof/Waste drainage to street Cleared 1/24/2024 COLIN LOREDO
Sewer availability Cleared 1/24/2024 COLIN LOREDO
Hydrant and Access approval Cleared 3/7/2024 JOHN CONNEALLY
Miscellaneous Cleared 3/11/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/24/2024 Partial Approval JOHN COLEMAN
Excavation/Setback/Form/Re-Bar 5/3/2024 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 5/3/2024 Partial Approval RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 5/6/2024 Approved RYAN SALAZAR
Footing/Foundation/Slab 5/6/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 5/28/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/17/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 7/8/2024 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 7/8/2024 Approved RYAN SALAZAR
Green Building Rough 7/8/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 7/8/2024 Partial Approval RYAN SALAZAR
PLUMBING-Rough 7/8/2024 Corrections Issued RYAN SALAZAR
Verify Sprinkler Sign Off 7/8/2024 Not Ready for Inspection RYAN SALAZAR
BUILDING-Rough-Frame 7/17/2024 Approved RYAN SALAZAR
PLUMBING-Rough 7/17/2024 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 7/17/2024 Approved RYAN SALAZAR
Insulation 7/24/2024 Corrections Issued LOUIS ESCOTO
Insulation 7/26/2024 Approved LOUIS ESCOTO
Drywall Nailing 8/1/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 8/16/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 8/16/2024 Approved RYAN SALAZAR
HVAC-Rough 8/16/2024 Approved RYAN SALAZAR
PLUMBING-Rough 8/16/2024 Approved RYAN SALAZAR
Rough-Elec/Plmb/HVAC 8/16/2024 Approved RYAN SALAZAR
Shower Pan 8/21/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 8/26/2024 Approved RYAN SALAZAR
Final 3/6/2025 Corrections Issued RYAN SALAZAR
Green Building Final 3/6/2025 Not Ready for Inspection RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 3/6/2025 SGSOV Not Required RYAN SALAZAR
Service/Power Release 3/6/2025 Not Ready for Inspection RYAN SALAZAR
Smoke Detectors 3/6/2025 Approved RYAN SALAZAR
Final 4/16/2025 Partial Inspection RYAN SALAZAR
Green Building Final 4/16/2025 Approved RYAN SALAZAR
Service/Power Release 4/16/2025 Not Ready for Inspection RYAN SALAZAR
Final 4/22/2025 OK to Issue CofO RYAN SALAZAR
Service/Power Release 4/22/2025 Approved RYAN SALAZAR