8664 N LAUREL CANYON BLVD 91352

Certificate Information: 8664 N LAUREL CANYON BLVD 91352

Application / Permit
23010-20000-05214
Plan Check / Job No.
B23VN17695
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 1-story Accessory Dwelling Unit (33'-7" x 25'-9") on north side of lot per per CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33(c)-(d), (g)
Permit Issued
Issued on 2/23/2024
Issuing Office
Current Status
CofO Issued on 12/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/26/2023 APPLICANT
Assigned to Plan Check Engineer 1/19/2024 VAHAN JIVALAGIAN
Corrections Issued 1/24/2024 VAHAN JIVALAGIAN
Quality Review Completed 1/29/2024 OMID HEDAYAT
Building Plans Picked Up 1/29/2024 APPLICANT
Plan Check Approved 2/23/2024 VAHAN JIVALAGIAN
Issued 2/23/2024 APPLICANT
CofO in Progress 11/18/2024 MATTHEW NELSON
Permit Finaled 12/17/2024 RUBEN SALAS
CofO Issued 12/17/2024 RUBEN SALAS
Permit Finaled 12/17/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/29/2024 LEE GUILBEAUX
Clean Up Green Up Cleared 1/29/2024 ALEX VELA
Miscellaneous Cleared 1/29/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/30/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/30/2024 LEE GUILBEAUX
Sewer availability Cleared 2/8/2024 LEE GUILBEAUX
Low Impact Development (LID) Cleared 2/9/2024 PATRICK LOPEZ
Roof/Waste drainage to street Cleared 2/21/2024 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/28/2024 Partial Approval MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 4/3/2024 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 4/29/2024 Partial Approval MATTHEW NELSON
HVAC-Rough 5/10/2024 Approved MATTHEW NELSON
PLUMBING-Rough 5/14/2024 Approved MATTHEW NELSON
Underground Mechanical 5/14/2024 Approved MATTHEW NELSON
BUILDING-Rough-Frame 5/17/2024 Approved MATTHEW NELSON
Green Building Rough 5/17/2024 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 5/17/2024 Approved MATTHEW NELSON
Insulation 5/24/2024 Approved MATTHEW NELSON
Interior/Exterior Lathing 5/24/2024 Approved MATTHEW NELSON
Shower Pan 5/24/2024 Approved MATTHEW NELSON
Drywall Nailing 5/29/2024 Approved MATTHEW NELSON
Service/Power Release 8/5/2024 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Final 8/6/2024 Approved MATTHEW NELSON
ELECTRICAL-Final 10/28/2024 Not Ready for Inspection MATTHEW NELSON
Final 10/28/2024 Not Ready for Inspection MATTHEW NELSON
Footing/Foundation/Slab 10/28/2024 Approved MATTHEW NELSON
Green Building Final 10/28/2024 Approved MATTHEW NELSON
HVAC-Final 10/28/2024 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Final 10/28/2024 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 10/28/2024 SGSOV Not Required MATTHEW NELSON
Service/Power Release 10/28/2024 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 10/28/2024 Not Ready for Inspection MATTHEW NELSON
HVAC-Final 11/1/2024 Corrections Issued MATTHEW NELSON
ELECTRICAL-Final 11/12/2024 Corrections Issued MISAEL ESPARZA
Final 11/12/2024 Not Ready for Inspection MISAEL ESPARZA
Service/Power Release 11/12/2024 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 11/12/2024 Approved MISAEL ESPARZA
ELECTRICAL-Final 11/15/2024 Approved MATTHEW NELSON
Service/Power Release 11/15/2024 Approved MATTHEW NELSON
Final 11/18/2024 OK to Issue CofO MATTHEW NELSON