11087 N DE FOE AVE 91331
Certificate Information: 11087 N DE FOE AVE 91331
- Application / Permit
- 23010-20000-05168
- Plan Check / Job No.
- B23VN17573
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT (1095 SQ.FT.) _[PER LAMC 12.22 A.33(c) and (d)]_ BUIDLING TO BE TYPE VA CONSTRUCTION (PER FIRE DEPARTMENT).
- Permit Issued
- Issued on 4/8/2024
- Issuing Office
- Current Status
- CofO Issued on 2/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2024 | DAWN MC NULTY |
| Corrections Issued | 1/25/2024 | DAWN MC NULTY |
| Quality Review Completed | 1/26/2024 | OMID HEDAYAT |
| Plan Check Approved | 3/17/2024 | DAWN MC NULTY |
| Issued | 4/8/2024 | APPLICANT |
| CofO in Progress | 1/6/2026 | MICHEL ABAJAN |
| Permit Finaled | 2/10/2026 | RUBEN SALAS |
| CofO Issued | 2/10/2026 | RUBEN SALAS |
| Permit Finaled | 2/10/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/29/2024 | CARLOS RAMIREZ |
| Clean Up Green Up | Cleared | 1/31/2024 | STEVEN WECHSLER |
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 2/2/2024 | CARLOS RAMIREZ |
| Low Impact Development (LID) | Cleared | 2/27/2024 | LUIS CRUZ |
| Permit | Cleared | 2/27/2024 | CARLOS RAMIREZ |
| Roof/Waste drainage to street | Cleared | 2/27/2024 | CARLOS RAMIREZ |
| Hydrant and Access approval | Cleared | 3/6/2024 | KURT CORRAL |
Contact Information
| Contractor | Triple O Construction; Lic. No.: 562974-B | , |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/26/2024 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 4/26/2024 | Corrections Issued | MICHEL ABAJAN |
| Underground Mechanical | 4/26/2024 | Approved | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 4/30/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 5/8/2024 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2024 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 5/20/2024 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/28/2024 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 6/28/2024 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2024 | Partial Approval | MICHEL ABAJAN |
| HVAC-Rough | 6/28/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 6/28/2024 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 6/28/2024 | Approved | MICHEL ABAJAN |
| Deputy Wood Construction | 7/1/2024 | Conditional Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/3/2024 | Approved | MICHEL ABAJAN |
| Insulation | 7/9/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 7/9/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 7/22/2024 | Approved | MICHEL ABAJAN |
| Shower Pan | 7/22/2024 | Approved | MICHEL ABAJAN |
| Grounding or Bonding | 8/30/2024 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Final | 10/15/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 10/15/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 10/15/2024 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 10/15/2024 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 10/15/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 10/15/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 10/15/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 10/28/2024 | No Access for Inspection | MICHEL ABAJAN |
| Final | 10/28/2024 | No Access for Inspection | MICHEL ABAJAN |
| HVAC-Final | 10/28/2024 | No Access for Inspection | MICHEL ABAJAN |
| PLUMBING-Final | 10/28/2024 | No Access for Inspection | MICHEL ABAJAN |
| Service/Power Release | 10/28/2024 | No Access for Inspection | MICHEL ABAJAN |
| Final | 10/30/2024 | Corrections Issued | MICHEL ABAJAN |
| Service/Power Release | 10/30/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 12/9/2024 | OK to Issue CofO | MICHEL ABAJAN |
| Pre-Inspection | 10/14/2025 | Corrections Issued | MICHEL ABAJAN |
| Service/Power Release | 12/26/2025 | Approved | JENNIFER RABUCHIN |