11087 N DE FOE AVE 91331

Certificate Information: 11087 N DE FOE AVE 91331

Application / Permit
23010-20000-05168
Plan Check / Job No.
B23VN17573
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT (1095 SQ.FT.) _[PER LAMC 12.22 A.33(c) and (d)]_ BUIDLING TO BE TYPE VA CONSTRUCTION (PER FIRE DEPARTMENT).
Permit Issued
Issued on 4/8/2024
Issuing Office
Current Status
CofO Issued on 2/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/22/2023 APPLICANT
Assigned to Plan Check Engineer 1/19/2024 DAWN MC NULTY
Corrections Issued 1/25/2024 DAWN MC NULTY
Quality Review Completed 1/26/2024 OMID HEDAYAT
Plan Check Approved 3/17/2024 DAWN MC NULTY
Issued 4/8/2024 APPLICANT
CofO in Progress 1/6/2026 MICHEL ABAJAN
Permit Finaled 2/10/2026 RUBEN SALAS
CofO Issued 2/10/2026 RUBEN SALAS
Permit Finaled 2/10/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/29/2024 CARLOS RAMIREZ
Clean Up Green Up Cleared 1/31/2024 STEVEN WECHSLER
Eng Process Fee Ord 176,300 Cleared 2/2/2024 CARLOS RAMIREZ
Sewer availability Cleared 2/2/2024 CARLOS RAMIREZ
Low Impact Development (LID) Cleared 2/27/2024 LUIS CRUZ
Permit Cleared 2/27/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 2/27/2024 CARLOS RAMIREZ
Hydrant and Access approval Cleared 3/6/2024 KURT CORRAL

Contact Information

Contractor Triple O Construction; Lic. No.: 562974-B       ,
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/26/2024 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 4/26/2024 Corrections Issued MICHEL ABAJAN
Underground Mechanical 4/26/2024 Approved MICHEL ABAJAN
Deputy Drilled-In Anchors 4/30/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 5/8/2024 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 5/20/2024 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 5/20/2024 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 6/28/2024 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 6/28/2024 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 6/28/2024 Partial Approval MICHEL ABAJAN
HVAC-Rough 6/28/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 6/28/2024 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 6/28/2024 Approved MICHEL ABAJAN
Deputy Wood Construction 7/1/2024 Conditional Approval MICHEL ABAJAN
BUILDING-Rough-Frame 7/3/2024 Approved MICHEL ABAJAN
Insulation 7/9/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 7/9/2024 Approved MICHEL ABAJAN
Drywall Nailing 7/22/2024 Approved MICHEL ABAJAN
Shower Pan 7/22/2024 Approved MICHEL ABAJAN
Grounding or Bonding 8/30/2024 Partial Approval MATTHEW NELSON
ELECTRICAL-Final 10/15/2024 Corrections Issued JENNIFER RABUCHIN
Final 10/15/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 10/15/2024 Approved JENNIFER RABUCHIN
HVAC-Final 10/15/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/15/2024 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 10/15/2024 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 10/15/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/28/2024 No Access for Inspection MICHEL ABAJAN
Final 10/28/2024 No Access for Inspection MICHEL ABAJAN
HVAC-Final 10/28/2024 No Access for Inspection MICHEL ABAJAN
PLUMBING-Final 10/28/2024 No Access for Inspection MICHEL ABAJAN
Service/Power Release 10/28/2024 No Access for Inspection MICHEL ABAJAN
Final 10/30/2024 Corrections Issued MICHEL ABAJAN
Service/Power Release 10/30/2024 Not Ready for Inspection MICHEL ABAJAN
Final 12/9/2024 OK to Issue CofO MICHEL ABAJAN
Pre-Inspection 10/14/2025 Corrections Issued MICHEL ABAJAN
Service/Power Release 12/26/2025 Approved JENNIFER RABUCHIN