405 S CLIFFWOOD AVE 90049
Certificate Information: 405 S CLIFFWOOD AVE 90049
- Application / Permit
- 23010-20000-05150
- Plan Check / Job No.
- B23VN17522
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 125'-5" X 73'-4" SINGLE FAMILY DWELLING WITH BASEMENT AND ATTACHED 3 CAR GARAGE AND PATIO COVERS/ TRELLIS ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT
- Permit Issued
- Issued on 5/30/2024
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 5/30/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2024 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 1/24/2024 | SEWADA ZADOORIAN MILAGARDI |
| Building Plans Picked Up | 1/26/2024 | APPLICANT |
| Quality Review Completed | 3/12/2024 | STEVEN KIM |
| Applicant returned to address corrections | 3/12/2024 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 4/1/2024 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 4/23/2024 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 4/25/2024 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 5/28/2024 | SEWADA ZADOORAN MILAGARDI |
| Issued | 5/30/2024 | APPLICANT |
Permit Application Clearance Information
| Specific Plan | Cleared | 1/31/2024 | ALESSANDRO MERCURI |
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2024 | LIAM ODONOVAN |
| Sewer availability | Cleared | 2/1/2024 | LIAM ODONOVAN |
| Miscellaneous | Cleared | 2/6/2024 | SPENCER WEJROWSKI |
| Trees in Parkway | Cleared | 2/6/2024 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 3/2/2024 | GILBERT URREA |
| Low Impact Development (LID) | Cleared | 4/12/2024 | LUIS LUVANO |
| Permit | Cleared | 4/16/2024 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 4/29/2024 | DINAH GARIN |
| Work Adjacent to Public Way | Cleared | 5/16/2024 | LIAM ODONOVAN |
| Miscellaneous | Cleared | 5/22/2024 | DINAH GARIN |
| Excavation more than 5-ft deep | Cleared | 5/28/2024 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 5/28/2024 | SEWADA ZADOORAN MILAGARDI |
| Grading Pre-Inspection | Cleared | 5/28/2024 | SEWADA ZADOORAN MILAGARDI |
Contact Information
| Contractor | E T Development Inc; Lic. No.: 994749-B | 7256 BELLAIRE AVENUE NORTH HOLLYWOOD, CA 91605 |
| Engineer | Daneshfar,, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Engineer | Mixter,, Thomas J; Lic. No.: C51041 | 2345 COUNTY RD 630 DEL RIO, TX 78840 |
| Engineer | Tani,, Jason; Lic. No.: C58271 | 5296 VIA PATRICIA THOUSAND OAKS, CA 91320 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/12/2024 | Partial Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 8/7/2024 | Partial Approval | ARAM AVEDISIAN |
| Deputy Reinf. Concrete | 8/13/2024 | Conditional Approval | ARAM AVEDISIAN |
| Deputy Reinf. Concrete | 8/27/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 8/28/2024 | Partial Approval | JESUS RODRIGUEZ |
| Deputy Reinf. Concrete | 9/3/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Deputy Reinf. Concrete | 9/18/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 9/19/2024 | Partial Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 11/8/2024 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 11/8/2024 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 11/12/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Underground Mechanical | 11/12/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 11/20/2024 | Partial Approval | JESUS RODRIGUEZ |
| Deputy Steel/Welding | 11/21/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Deputy Reinf. Concrete | 11/22/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Steel/Welding | 11/27/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2025 | Partial Approval | JESUS RODRIGUEZ |
| Deputy Wood Construction | 2/12/2025 | Conditional Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2025 | Partial Approval | JESUS RODRIGUEZ |
| HVAC-Rough | 3/14/2025 | Corrections Issued | HERBERT GIRON |
| Special/Order Compliance | 3/14/2025 | Partial Inspection | BOBBY KEY |
| HVAC-Rough | 3/18/2025 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 3/18/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 4/1/2025 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 4/1/2025 | Partial Approval | HERBERT GIRON |
| Shower Pan | 4/1/2025 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Rough | 4/4/2025 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 4/7/2025 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 4/7/2025 | Partial Approval | HERBERT GIRON |
| Verify Sprinkler Sign Off | 4/7/2025 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 4/15/2025 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Rough | 4/15/2025 | Not Ready for Inspection | HERBERT GIRON |
| Green Building Rough | 4/15/2025 | Partial Approval | HERBERT GIRON |
| ELECTRICAL-Rough | 4/17/2025 | Corrections Issued | HERBERT GIRON |
| Sewer | 4/22/2025 | Approved | HERBERT GIRON |
| Underground Mechanical | 4/22/2025 | Approved | HERBERT GIRON |
| Insulation | 5/5/2025 | Conditional Approval | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 5/8/2025 | Partial Approval | HERBERT GIRON |
| Shower Pan | 5/8/2025 | Approved | HERBERT GIRON |
| Drywall Nailing | 5/16/2025 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 2/2/2026 | Not Ready for Inspection | HERBERT GIRON |
| Footing/Foundation/Slab | 2/2/2026 | Partial Approval | HERBERT GIRON |
| Green Building Rough | 2/2/2026 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 3/4/2026 | Conditional Approval | HERBERT GIRON |
| Interior/Exterior Lathing | 3/4/2026 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 3/4/2026 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 4/20/2026 | Conditional Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 5/12/2026 | Approved | HERBERT GIRON |