10130 N OAK PARK AVE 91325

Certificate Information: 10130 N OAK PARK AVE 91325

Application / Permit
23010-20000-05125
Plan Check / Job No.
B23VN17472
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New irregular shaped one story 41' 6" x 37' ADU per LAMC 12.22 A.33 (c)-(d) with attached patio cover. All work done per WFPP.
Permit Issued
Issued on 6/7/2024
Issuing Office
Current Status
CofO Issued on 3/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2023 APPLICANT
Assigned to Plan Check Engineer 1/11/2024 NAREG ATARIAN
Corrections Issued 1/17/2024 NAREG ATARIAN
Quality Review Completed 1/24/2024 OMID HEDAYAT
Building Plans Picked Up 1/24/2024 APPLICANT
Plan Check Approved 6/7/2024 NAREG ATARIAN
Issued 6/7/2024 APPLICANT
CofO in Progress 3/7/2025 JAVIER RAMOS JR
Permit Finaled 3/15/2025 RUBEN SALAS
CofO Issued 3/15/2025 RUBEN SALAS
Permit Finaled 3/15/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/25/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 1/29/2024 CARLOS RAMIREZ
Sewer availability Cleared 1/29/2024 CARLOS RAMIREZ
Hydrant and Access approval Cleared 5/20/2024 KURT CORRAL
Construction near power lines Cleared 5/30/2024 WALTER RAMIREZ
Construction within easement Cleared 5/30/2024 WALTER RAMIREZ
Low Impact Development (LID) Cleared 6/5/2024 LUIS LUVANO
Roof/Waste drainage to street Cleared 6/6/2024 CARLOS AGUILERA
GPI Written Notices Cleared 6/7/2024 GERMAN RODRIGUEZ MENDOZA
Grading Pre-Inspection Cleared 6/7/2024 GERMAN RODRIGUEZ MENDOZA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/17/2024 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 7/26/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 7/26/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 7/30/2024 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 8/1/2024 Partial Approval JAVIER RAMOS JR
Special/Order Compliance 8/1/2024 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 8/16/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 8/27/2024 Approved JAVIER RAMOS JR
Green Building Rough 8/27/2024 Approved JAVIER RAMOS JR
HVAC-Rough 8/27/2024 Approved JAVIER RAMOS JR
Insulation 8/27/2024 Partial Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 8/27/2024 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 8/27/2024 Approved JAVIER RAMOS JR
Shower Pan 8/27/2024 Approved JAVIER RAMOS JR
Insulation 8/29/2024 Partial Approval LOUIS ESCOTO
Shower Pan 8/29/2024 Approved LOUIS ESCOTO
BUILDING-Rough-Frame 9/3/2024 Approved JAVIER RAMOS JR
Drywall Nailing 9/3/2024 Approved LOUIS ESCOTO
Interior/Exterior Lathing 9/3/2024 Approved LOUIS ESCOTO
Sewer 9/16/2024 Approved JAVIER RAMOS JR
Final 11/26/2024 No Access for Inspection JAVIER RAMOS JR
ELECTRICAL-Final 1/23/2025 Corrections Issued JAVIER RAMOS JR
Final 1/23/2025 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 1/23/2025 Not Ready for Inspection JAVIER RAMOS JR
Green Building Final 1/23/2025 Approved JAVIER RAMOS JR
HVAC-Final 1/23/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 1/23/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 1/23/2025 SGSOV Not Required JAVIER RAMOS JR
Smoke Detectors 1/23/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 3/5/2025 Approved JAVIER RAMOS JR
Final 3/5/2025 OK to Issue CofO JAVIER RAMOS JR
Footing/Foundation/Slab 3/5/2025 Approved JAVIER RAMOS JR
Service/Power Release 3/5/2025 Approved JAVIER RAMOS JR