10130 N OAK PARK AVE 91325
Certificate Information: 10130 N OAK PARK AVE 91325
- Application / Permit
- 23010-20000-05125
- Plan Check / Job No.
- B23VN17472
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New irregular shaped one story 41' 6" x 37' ADU per LAMC 12.22 A.33 (c)-(d) with attached patio cover. All work done per WFPP.
- Permit Issued
- Issued on 6/7/2024
- Issuing Office
- Current Status
- CofO Issued on 3/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2024 | NAREG ATARIAN |
| Corrections Issued | 1/17/2024 | NAREG ATARIAN |
| Quality Review Completed | 1/24/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 1/24/2024 | APPLICANT |
| Plan Check Approved | 6/7/2024 | NAREG ATARIAN |
| Issued | 6/7/2024 | APPLICANT |
| CofO in Progress | 3/7/2025 | JAVIER RAMOS JR |
| Permit Finaled | 3/15/2025 | RUBEN SALAS |
| CofO Issued | 3/15/2025 | RUBEN SALAS |
| Permit Finaled | 3/15/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/25/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 1/29/2024 | CARLOS RAMIREZ |
| Hydrant and Access approval | Cleared | 5/20/2024 | KURT CORRAL |
| Construction near power lines | Cleared | 5/30/2024 | WALTER RAMIREZ |
| Construction within easement | Cleared | 5/30/2024 | WALTER RAMIREZ |
| Low Impact Development (LID) | Cleared | 6/5/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 6/6/2024 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 6/7/2024 | GERMAN RODRIGUEZ MENDOZA |
| Grading Pre-Inspection | Cleared | 6/7/2024 | GERMAN RODRIGUEZ MENDOZA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/17/2024 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 7/26/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 7/26/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 7/30/2024 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 8/1/2024 | Partial Approval | JAVIER RAMOS JR |
| Special/Order Compliance | 8/1/2024 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 8/27/2024 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 8/27/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 8/27/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 8/27/2024 | Partial Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 8/27/2024 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 8/27/2024 | Approved | JAVIER RAMOS JR |
| Shower Pan | 8/27/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 8/29/2024 | Partial Approval | LOUIS ESCOTO |
| Shower Pan | 8/29/2024 | Approved | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 9/3/2024 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 9/3/2024 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 9/3/2024 | Approved | LOUIS ESCOTO |
| Sewer | 9/16/2024 | Approved | JAVIER RAMOS JR |
| Final | 11/26/2024 | No Access for Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Final | 1/23/2025 | Corrections Issued | JAVIER RAMOS JR |
| Final | 1/23/2025 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 1/23/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Final | 1/23/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 1/23/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 1/23/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 1/23/2025 | SGSOV Not Required | JAVIER RAMOS JR |
| Smoke Detectors | 1/23/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 3/5/2025 | Approved | JAVIER RAMOS JR |
| Final | 3/5/2025 | OK to Issue CofO | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 3/5/2025 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 3/5/2025 | Approved | JAVIER RAMOS JR |