1342 S THAYER AVE 90024

Certificate Information: 1342 S THAYER AVE 90024

Application / Permit
23010-20000-05118
Plan Check / Job No.
B23VN17441
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ ATTACHED GARAGE & BASEMENT (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 1/29/2025
Issuing Office
West Los Angeles
Current Status
Issued on 1/29/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/20/2023 APPLICANT
Assigned to Plan Check Engineer 1/11/2024 NILOOFAR MEHRAIN
Corrections Issued 1/26/2024 NILOOFAR MEHRAIN
Quality Review Completed 2/8/2024 JASON HEALEY
Building Plans Picked Up 2/12/2024 APPLICANT
Applicant returned to address corrections 5/16/2024 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/27/2024 NILOOFAR MEHRAIN
Applicant returned to address corrections 9/19/2024 NILOOFAR MEHRAIN
Applicant returned to address corrections 10/8/2024 NILOOFAR MEHRAIN
Applicant returned to address corrections 1/7/2025 NILOOFAR MEHRAIN
Plan Check Approved 1/21/2025 NILOOFAR MEHRAIN
Issued 1/29/2025 APPLICANT

Permit Application Clearance Information

GPI Written Notices Cleared 5/16/2024 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 5/16/2024 NILOOFAR MEHRAIN
ZA Case Cleared 6/28/2024 JACQUELINE TORRES
Permit Cleared 6/30/2024 BRENDEN HAWK
Eng Process Fee Ord 176,300 Cleared 7/10/2024 BRENDEN HAWK
Sewer availability Cleared 7/10/2024 BRENDEN HAWK
Excavation more than 5-ft deep Cleared 8/27/2024 CALOSHA APPROVED
Hydrant and Access approval Cleared 8/28/2024 KURT CORRAL
Trees in Parkway Cleared 9/4/2024 ADALBERTO VERA
Low Impact Development (LID) Cleared 12/17/2024 ERNEST TSE
Roof/Waste drainage to street Cleared 12/20/2024 LIAM ODONOVAN

Contact Information

Architect Jazayeri,, Siavash; Lic. No.: C22240 20230 WELLS DR      WOODLAND HILLS, CA 91364
Contractor Delta West Construction; Lic. No.: 794816-B 132 S LA PEER DR      BEVERLY HILLS, CA 90211
Engineer Saljooghi,, Sanjar; Lic. No.: C53610 23265 PARK ENSENADA      CALABASAS, CA 91302

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Floor/Roof Diaphrgm/Shear Wall 6/8/2026   
HVAC-Rough 6/8/2026   

Inspection Request History

Pre-Inspection 2/12/2025 Corrections Issued KIRK SANDERS
Pre-Inspection 3/5/2025 Partial Inspection KIRK SANDERS
Special/Order Compliance 3/6/2025 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 8/26/2025 Partial Approval SEAN HAUPT
METHANE-Barrier 8/26/2025 Not Ready for Inspection SEAN HAUPT
METHANE-Subgrade 8/26/2025 Not Ready for Inspection SEAN HAUPT
Footing/Foundation/Slab 10/9/2025 Partial Approval MICHAEL ALLEN
METHANE-Barrier 10/9/2025 Not Ready for Inspection MICHAEL ALLEN
METHANE-Subgrade 10/9/2025 Not Ready for Inspection MICHAEL ALLEN
Underground Mechanical 10/16/2025 Partial Approval MICHAEL ALLEN
Footing/Foundation/Slab 10/28/2025 Partial Approval MICHAEL ALLEN
METHANE-Rough 10/28/2025 Partial Approval MICHAEL ALLEN
METHANE-Subgrade 10/28/2025 Partial Approval MICHAEL ALLEN
METHANE-Barrier 11/14/2025 Corrections Issued MICHAEL ALLEN
METHANE-Subgrade 11/14/2025 Approved MICHAEL ALLEN
Deputy Methane Barrier 12/3/2025 Conditional Approval ANDREW NAVE
METHANE-Barrier 12/4/2025 Partial Approval MICHAEL ALLEN
Excavation/Setback/Form/Re-Bar 12/9/2025 Partial Approval MICHAEL ALLEN
Deputy Steel/Welding 12/17/2025 Conditional Approval ANDREW NAVE
Sewer 12/18/2025 Corrections Issued MICHAEL ALLEN
Deputy Steel/Welding 12/22/2025 Conditional Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 12/24/2025 Partial Approval MICHAEL ALLEN
METHANE-Rough 12/24/2025 Partial Approval MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 1/6/2026 Partial Approval MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 1/13/2026 Corrections Issued MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 1/22/2026 Conditional Approval MICHAEL ALLEN
Deputy Drilled-In Anchors 5/14/2026 Conditional Approval BOBBY KEY
Deputy Steel/Welding 5/14/2026 Conditional Approval BOBBY KEY
ELECTRICAL-Rough 5/15/2026 Partial Approval ANTHONY EGSON
HVAC-Rough 5/15/2026 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 5/19/2026 Approved ANTHONY EGSON