- Application / Permit
- 23010-20000-05098
- Plan Check / Job No.
- B23VN17408
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan ADDITION AND REMODEL TO EXISTING TWO STORY SFD AND REMOVE EXISTING ATTACHED GARAGE 1 OF 2 *** BUILDING TO BE EQUIPPED WITH NFPA-13D FIRE SPRINKLERS THROUGHOUT***
- Permit Issued
- Issued on 4/11/2025
- Issuing Office
- Current Status
- Issued on 4/11/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2024 | CRYSTEL MAALOUF |
| Corrections Issued | 1/24/2024 | CRYSTEL MAALOUF |
| Quality Review Completed | 1/25/2024 | GARO TELMI |
| Applicant returned to address corrections | 3/13/2025 | CRYSTEL MAALOUF |
| Plan Check Approved | 3/27/2025 | CRYSTEL MAALOUF |
| Plan Check Approved | 4/2/2025 | CRYSTEL MAALOUF |
| Issued | 4/11/2025 | APPLICANT |
Permit Application Clearance Information
| ZI | Cleared | 9/5/2024 | ASHLEY RODARTE |
| Grading Pre-Inspection | Cleared | 9/13/2024 | ALEXANDER HELFER |
| Eng Process Fee Ord 176,300 | Cleared | 10/12/2024 | BRYAN GODINEZ |
| Sewer availability | Cleared | 10/12/2024 | BRYAN GODINEZ |
| Hydrant and Access approval | Cleared | 1/8/2025 | JOHN CONNEALLY |
| Low Impact Development (LID) | Cleared | 2/26/2025 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 2/28/2025 | JESSICA OPINION |
| GPI Written Notices | Cleared | 3/27/2025 | CRYSTEL MAALOUF |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/10/2025 | Partial Approval | JOHN KIDWELL |
| Deputy Drilled-In Anchors | 7/31/2025 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 8/7/2025 | Partial Approval | JOHN KIDWELL |
| Underground Mechanical | 8/7/2025 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 8/15/2025 | Conditional Approval | JOHN KIDWELL |
| Deputy Reinf. Concrete | 8/19/2025 | Partial Approval | JOHN KIDWELL |
| Deputy Other (see comments) | 9/9/2025 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2025 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2025 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 10/23/2025 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 11/7/2025 | Approved | JOHN KIDWELL |
| Deputy Wood Construction | 11/10/2025 | Conditional Approval | HENRY KIM |
| ELECTRICAL-Rough | 12/10/2025 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2025 | Partial Approval | JOHN KIDWELL |
| Deputy Reinf. Concrete | 1/28/2026 | Partial Approval | JOHN KIDWELL |
| Insulation | 2/5/2026 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 2/5/2026 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 2/12/2026 | Approved | JOHN KIDWELL |