20935 W SATICOY ST 91304
Certificate Information: 20935 W SATICOY ST 91304
- Application / Permit
- 23010-20000-05082
- Plan Check / Job No.
- B23VN17371
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan NEW DETACHED ACCESSORY DWELLING UNIT 1200 sq ft ADU CHECKED PER LAMC 12.22 A.33 (C)-(D)
- Permit Issued
- Issued on 3/22/2024
- Issuing Office
- Current Status
- CofO Issued on 3/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2024 | SUNMIN LEE |
| Corrections Issued | 1/12/2024 | SUNMIN LEE |
| Quality Review Completed | 1/12/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 2/29/2024 | SUNMIN LEE |
| Plan Check Approved | 3/13/2024 | SUNMIN LEE |
| Issued | 3/22/2024 | APPLICANT |
| CofO in Progress | 1/12/2026 | ALEXANDER HANDY |
| No Progress | 3/2/2026 | ROBERT GOLD |
| CofO in Progress | 3/2/2026 | ROBERT GOLD |
| Permit Finaled | 3/26/2026 | JOHN JANSON |
| CofO Issued | 3/26/2026 | JOHN JANSON |
| Permit Finaled | 3/26/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/17/2024 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2024 | BRYAN GODINEZ |
| Sewer availability | Cleared | 1/19/2024 | BRYAN GODINEZ |
| Low Impact Development (LID) | Cleared | 2/21/2024 | LUIS CRUZ |
| Roof/Waste drainage to street | Cleared | 2/27/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/4/2024 | Corrections Issued | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 10/9/2024 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 10/28/2024 | Partial Inspection | ALEXANDER HANDY |
| PLUMBING-Rough | 10/28/2024 | Partial Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 2/3/2025 | Partial Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 2/3/2025 | Approved | ALEXANDER HANDY |
| Green Building Rough | 2/3/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| PLUMBING-Rough | 2/3/2025 | Corrections Issued | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 2/3/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Interior/Exterior Lathing | 2/20/2025 | Partial Approval | ALEXANDER HANDY |
| Insulation | 2/27/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| HVAC-Rough | 3/11/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Insulation | 3/11/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Interior/Exterior Lathing | 3/11/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 3/14/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Rough | 3/14/2025 | Approved | GEVORK IPCHYAN |
| HVAC-Rough | 3/14/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 3/14/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Shower Pan | 3/14/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Verify Sprinkler Sign Off | 3/14/2025 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 3/18/2025 | Approved | ALEXANDER HANDY |
| Deputy Wood Construction | 3/18/2025 | Conditional Approval | ALEXANDER HANDY |
| HVAC-Rough | 3/18/2025 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 3/18/2025 | Approved | ALEXANDER HANDY |
| Shower Pan | 3/18/2025 | Approved | ALEXANDER HANDY |
| Special/Order Compliance | 3/18/2025 | Corrections Issued | ALEXANDER HANDY |
| Drywall Nailing | 3/21/2025 | Partial Approval | JEFFREY HARTLINE |
| Insulation | 3/21/2025 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 3/27/2025 | Approved | ALEXANDER HANDY |
| Final | 8/27/2025 | Corrections Issued | ALEXANDER HANDY |
| Footing/Foundation/Slab | 8/27/2025 | Approved | ALEXANDER HANDY |
| Green Building Final | 8/27/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 8/27/2025 | SGSOV Not Ready | ALEXANDER HANDY |
| Service/Power Release | 8/27/2025 | Not Required | ALEXANDER HANDY |
| Smoke Detectors | 8/27/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 1/8/2026 | Approved | ALEXANDER HANDY |
| Final | 1/8/2026 | OK to Issue CofO | ALEXANDER HANDY |
| HVAC-Final | 1/8/2026 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 1/8/2026 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 1/8/2026 | SGSOV Approved | ALEXANDER HANDY |