7519 N ETON AVE 91303

Certificate Information: 7519 N ETON AVE 91303

Application / Permit
23010-20000-05078
Plan Check / Job No.
B23VN17326
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: NEW TWO STORY DETACHED ACCESSORY DWELLING UNIT PER ORDINANCE LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 5/23/2025
Issuing Office
Current Status
Issued on 5/23/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/19/2023 APPLICANT
Assigned to Plan Check Engineer 12/21/2023 JAD BASMA
Corrections Issued 12/28/2023 JAD BASMA
Quality Review Completed 1/4/2024 PRANITA SHAH
Applicant returned to address corrections 4/25/2024 JAD BASMA
Plan Check Approved 5/16/2024 JAD BASMA
Issued 5/23/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/17/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/18/2024 CARLOS AGUILERA
Sewer availability Cleared 1/18/2024 CARLOS AGUILERA
Low Impact Development (LID) Cleared 5/9/2024 ERNEST TSE
Roof/Waste drainage to street Cleared 5/13/2024 CARLOS AGUILERA

Contact Information

Contractor Kleen Construction Corporation; Lic. No.: 1106748-B 530 S LAKE AVE #374      PASADENA, CA 91101

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/4/2025 Partial Approval ALEXANDER HANDY
Sewer 6/4/2025 Approved ALEXANDER HANDY
Underground Mechanical 6/4/2025 Approved ALEXANDER HANDY
Footing/Foundation/Slab 7/2/2025 Approved SCOTT SOBEL
Floor/Roof Diaphrgm/Shear Wall 7/30/2025 Corrections Issued SCOTT SOBEL
Floor/Roof Diaphrgm/Shear Wall 8/4/2025 Partial Approval SCOTT SOBEL
BUILDING-Rough-Frame 10/10/2025 Corrections Issued MORRIS JACKSON
ELECTRICAL-Rough 10/10/2025 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 10/10/2025 Partial Approval MORRIS JACKSON
Gas Test 10/10/2025 Approved MORRIS JACKSON
HVAC-Rough 10/10/2025 Approved MORRIS JACKSON
PLUMBING-Rough 10/10/2025 Approved MORRIS JACKSON
Wood Frame 10/10/2025 Not Ready for Inspection MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 10/24/2025 Approved JUAN ALVARADO
Shower Pan 10/24/2025 Not Ready for Inspection JUAN ALVARADO
BUILDING-Rough-Frame 11/3/2025 Conditional Approval KRISTEN CAUSEY
Green Building Rough 11/3/2025 Approved KRISTEN CAUSEY
Insulation 11/3/2025 Approved KRISTEN CAUSEY
Shower Pan 11/3/2025 Approved KRISTEN CAUSEY
Drywall Nailing 11/25/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 11/25/2025 Partial Approval JEFFREY HARTLINE
Interior/Exterior Lathing 1/6/2026 Approved ALEXANDER HANDY