- NEW 57'X 38' TWO STORY SFD WITH ATTACHED 2 CAR GARAGE, NFPA-13D FIRE SPRINKLERS REQUIRED THOURGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 2/16/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/21/2023 | RARES BODEA |
| Corrections Issued | 12/26/2023 | RARES BODEA |
| Quality Review Completed | 12/28/2023 | STEVEN KIM |
| Building Plans Picked Up | 1/3/2024 | APPLICANT |
| Plan Check Approved | 2/16/2024 | RARES BODEA |
| Issued | 2/16/2024 | APPLICANT |
| CofO in Progress | 10/24/2024 | CHRISTOPHER ROJAS |
| Permit Finaled | 11/1/2024 | DANIEL ORRANTE |
| CofO Issued | 11/1/2024 | DANIEL ORRANTE |
| Permit Finaled | 11/1/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/27/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/29/2024 | CARLOS AGUILERA |
| Trees in Parkway | Cleared | 2/6/2024 | ADALBERTO VERA |
| Permit | Cleared | 2/8/2024 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 2/12/2024 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 2/14/2024 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 2/14/2024 | CARLOS AGUILERA |
| ZI | Cleared | 2/16/2024 | JASON CHAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | PO BOX 7112 NORTHRIDGE, CA 91327 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/21/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Underground Mechanical | 3/21/2024 | Approved | CHRISTOPHER ROJAS |
| Deputy Reinf. Concrete | 3/26/2024 | Conditional Approval | JUAN VALENZUELA |
| Underground Mechanical | 3/28/2024 | Approved | CHRISTOPHER ROJAS |
| Deputy Wood Construction | 4/16/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2024 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Deputy Wood Construction | 5/3/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Deputy Wood Construction | 5/14/2024 | Conditional Approval | JUAN VALENZUELA |
| HVAC-Rough | 5/16/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 5/17/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 5/21/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 5/24/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Green Building Rough | 5/24/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 5/24/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 6/3/2024 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 6/6/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 6/6/2024 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 6/6/2024 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 6/6/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 6/11/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 6/14/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Drywall Nailing | 6/17/2024 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 6/17/2024 | Approved | JUAN VALENZUELA |
| Underground Mechanical | 7/30/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Underground Mechanical | 8/2/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 10/1/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 10/1/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 10/1/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Final | 10/1/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Final | 10/1/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Final | 10/1/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 10/1/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 10/1/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 10/1/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 10/11/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 10/11/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Green Building Final | 10/11/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Final | 10/11/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 10/11/2024 | Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 10/11/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 10/22/2024 | Corrections Issued | JUAN VALENZUELA |
| Final | 10/24/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |