6829 N RANCHITO AVE 91405

Certificate Information: 6829 N RANCHITO AVE 91405

Application / Permit
23010-20000-05051
Plan Check / Job No.
B23VN17258
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20'-0" X 42'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) . ALL WORK DONE PER WFPP. NFPA 13D- FIRE SPRINKLER THRU-OUT.
Permit Issued
Issued on 3/12/2024
Issuing Office
Current Status
CofO Issued on 5/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2023 APPLICANT
Assigned to Plan Check Engineer 12/20/2023 ARTIN ZARUKIAN
Corrections Issued 12/26/2023 ARTIN ZARUKIAN
Building Plans Picked Up 12/26/2023 APPLICANT
Plan Check Approved 3/12/2024 PINANK PATEL
Issued 3/12/2024 APPLICANT
CofO in Progress 4/28/2025 RYAN SALAZAR
Permit Finaled 5/6/2025 RUBEN SALAS
CofO Issued 5/6/2025 RUBEN SALAS
Permit Finaled 5/6/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/27/2023 GABRIELLA TORRES
Low Impact Development (LID) Cleared 1/9/2024 ROGELIO CORTES
Eng Process Fee Ord 176,300 Cleared 1/11/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 1/11/2024 EDGAR ALCARAZ
Sewer availability Cleared 1/24/2024 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/3/2024 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 5/3/2024 Partial Approval RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 5/6/2024 Approved RYAN SALAZAR
Footing/Foundation/Slab 5/6/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 5/29/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/17/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 7/8/2024 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 7/8/2024 Approved RYAN SALAZAR
Green Building Rough 7/8/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 7/8/2024 Partial Approval RYAN SALAZAR
PLUMBING-Rough 7/8/2024 Partial Approval RYAN SALAZAR
Verify Sprinkler Sign Off 7/8/2024 Not Ready for Inspection RYAN SALAZAR
BUILDING-Rough-Frame 7/17/2024 Approved RYAN SALAZAR
PLUMBING-Rough 7/17/2024 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 7/17/2024 Approved RYAN SALAZAR
Insulation 7/24/2024 Corrections Issued LOUIS ESCOTO
Insulation 7/26/2024 Approved LOUIS ESCOTO
Drywall Nailing 8/1/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 8/16/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 8/16/2024 Approved RYAN SALAZAR
PLUMBING-Rough 8/16/2024 Approved RYAN SALAZAR
Rough-Elec/Plmb/HVAC 8/16/2024 Approved RYAN SALAZAR
Shower Pan 8/21/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 8/26/2024 Approved RYAN SALAZAR
Final 3/6/2025 Corrections Issued RYAN SALAZAR
Green Building Final 3/6/2025 Not Ready for Inspection RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 3/6/2025 SGSOV Not Required RYAN SALAZAR
Service/Power Release 3/6/2025 Not Ready for Inspection RYAN SALAZAR
Smoke Detectors 3/6/2025 Approved RYAN SALAZAR
Final 4/16/2025 Partial Inspection RYAN SALAZAR
Green Building Final 4/16/2025 Approved RYAN SALAZAR
Service/Power Release 4/16/2025 Not Ready for Inspection RYAN SALAZAR
Final 4/22/2025 OK to Issue CofO RYAN SALAZAR
Service/Power Release 4/22/2025 Approved RYAN SALAZAR