6026 N ST CLAIR AVE 91606

Certificate Information: 6026 N ST CLAIR AVE 91606

Application / Permit
23010-20000-05026
Plan Check / Job No.
B23VN17175
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 31'-6" X 40'-6" ONE STORY ACCESSORY DWELLING UNIT WITH ATTACHED PATIO COVER PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT
Permit Issued
Issued on 2/9/2024
Issuing Office
Current Status
CofO Issued on 2/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/14/2023 APPLICANT
Assigned to Plan Check Engineer 12/21/2023 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 12/26/2023 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 12/29/2023 STEVEN KIM
Building Plans Picked Up 12/29/2023 APPLICANT
Plan Check Approved 2/9/2024 SEWADA ZADOORAN MILAGARDI
Issued 2/9/2024 APPLICANT
CofO in Progress 1/24/2025 OGANES TARAKHCHYAN
Permit Finaled 2/18/2025 RUBEN SALAS
CofO Issued 2/18/2025 RUBEN SALAS
Permit Finaled 2/18/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/23/2024 EDGAR ALCARAZ
Low Impact Development (LID) Cleared 1/25/2024 TOMMY YIN
Eng Process Fee Ord 176,300 Cleared 1/29/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 1/29/2024 EDGAR ALCARAZ
Sewer availability Cleared 1/29/2024 EDGAR ALCARAZ
Hydrant and Access approval Cleared 1/31/2024 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/8/2024 Partial Approval JOSE AVILA
Excavation/Setback/Form/Re-Bar 3/13/2024 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 3/13/2024 Not Ready for Inspection JOSE AVILA
ELECTRICAL-Rough 3/14/2024 Not Ready for Inspection JOSE AVILA
Excavation/Setback/Form/Re-Bar 3/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 3/19/2024 Approved JOSE AVILA
Footing/Foundation/Slab 3/19/2024 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 4/1/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 4/4/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 4/18/2024 Corrections Issued JOSE AVILA
PLUMBING-Rough 4/18/2024 Not Ready for Inspection JOSE AVILA
HVAC-Rough 4/26/2024 Approved JOSE AVILA
PLUMBING-Rough 4/26/2024 Conditional Approval JOSE AVILA
ELECTRICAL-Rough 4/30/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 4/30/2024 Approved ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 4/30/2024 Approved ROBERTO PALACIOS-LOPEZ
Wood Frame 4/30/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Deputy Wood Construction 5/2/2024 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 5/3/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 5/3/2024 Conditional Approval ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 5/3/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 5/3/2024 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 5/3/2024 Approved ROBERTO PALACIOS-LOPEZ
MERV13>=Rough 5/3/2024 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 5/3/2024 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 5/6/2024 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 5/6/2024 Approved ROBERTO PALACIOS-LOPEZ
Wood Frame 5/6/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 5/8/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Drywall Nailing 5/14/2024 Approved OGANES TARAKHCHYAN
Underground Mechanical 8/21/2024 Not Ready for Inspection SALVADOR MARTINEZ
PLUMBING-Final 12/20/2024 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 12/27/2024 Approved OGANES TARAKHCHYAN
HVAC-Final 12/27/2024 Approved OGANES TARAKHCHYAN
Service/Power Release 12/27/2024 Approved OGANES TARAKHCHYAN
Smoke Detectors 12/27/2024 Approved OGANES TARAKHCHYAN
Final 1/23/2025 OK to Issue CofO OGANES TARAKHCHYAN
Green Building Final 1/23/2025 Approved OGANES TARAKHCHYAN
MERV13>=Final 1/23/2025 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 1/23/2025 SGSOV Approved OGANES TARAKHCHYAN