12078 W PEORIA ST 91352
Certificate Information: 12078 W PEORIA ST 91352
- Application / Permit
- 23010-20000-05021
- Plan Check / Job No.
- B23VN17158
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 1/28/2025
- Issuing Office
- Valley
- Current Status
- Issued on 1/28/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 12/20/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 1/18/2024 | APPLICANT |
| Plan Check Approved | 1/28/2025 | PINANK PATEL |
| Issued | 1/28/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/20/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/25/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/25/2024 | BIAINA HARITUNIAN |
| Low Impact Development (LID) | Cleared | 1/23/2025 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 1/23/2025 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Service/Power Release | 7/23/2026 Time Frame: 1-3 |
| Final | 7/23/2026 Time Frame: 1-3 |
Inspection Request History
| Footing/Foundation/Slab | 2/10/2025 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 2/10/2025 | Partial Inspection | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 2/14/2025 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 2/14/2025 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 2/14/2025 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/12/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2025 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 3/12/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 3/12/2025 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/21/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2025 | Partial Approval | MATTHEW NELSON |
| Green Building Rough | 3/21/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 3/21/2025 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 6/26/2025 | Partial Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 6/26/2025 | Partial Inspection | MATTHEW NELSON |
| Green Building Rough | 6/26/2025 | Partial Inspection | MATTHEW NELSON |
| HVAC-Rough | 6/26/2025 | Partial Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 6/26/2025 | Partial Inspection | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 6/26/2025 | Partial Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 7/1/2025 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 7/1/2025 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 7/2/2025 | Approved | MATTHEW NELSON |
| Green Building Rough | 7/2/2025 | Approved | MATTHEW NELSON |
| HVAC-Rough | 7/2/2025 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 7/2/2025 | Approved | MATTHEW NELSON |
| Insulation | 7/11/2025 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 7/11/2025 | Approved | MATTHEW NELSON |
| Drywall Nailing | 7/21/2025 | Approved | MICHAEL CORTEZ |
| Final | 10/14/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Final | 10/14/2025 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 10/14/2025 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 10/14/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 10/14/2025 | Approved | MATTHEW NELSON |
| Final | 11/19/2025 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 11/19/2025 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 11/19/2025 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 11/19/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 6/2/2026 | Partial Inspection | MATTHEW NELSON |
| Service/Power Release | 6/2/2026 | Partial Inspection | MATTHEW NELSON |