11933 W STAGG ST 91605
Certificate Information: 11933 W STAGG ST 91605
- Application / Permit
- 23010-20000-04978
- Plan Check / Job No.
- B23VN16994
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT WITH ATTACHED TRELLIS PATIO COVER PER LAMC 12.22 A.33(c) AND (d). NFPA 13D FIRE SPRINKLER SYSTEM REQUIRED.
- Permit Issued
- Issued on 6/3/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2023 | KAMYAR EMAMI |
| Corrections Issued | 12/16/2023 | KAMYAR EMAMI |
| Building Plans Picked Up | 4/9/2024 | APPLICANT |
| Applicant returned to address corrections | 5/1/2024 | ROSENDO MEDINA |
| Plan Check Approved | 5/21/2024 | ALEC MOUSAKHANIAN |
| Issued | 6/3/2024 | APPLICANT |
| CofO in Progress | 12/23/2024 | MATTHEW NELSON |
| Permit Finaled | 1/17/2025 | RUBEN SALAS |
| CofO Issued | 1/17/2025 | RUBEN SALAS |
| Permit Finaled | 1/17/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 1/8/2024 | NELSON RODRIGUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 1/23/2024 | EDGAR ALCARAZ |
| Low Impact Development (LID) | Cleared | 4/23/2024 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 4/23/2024 | CARLOS RAMIREZ |
| Construction near power lines | Cleared | 4/24/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 4/24/2024 | RIDWAN HARDY |
| Address approval | Cleared | 4/25/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/5/2024 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 6/12/2024 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 8/12/2024 | Approved | MATTHEW NELSON |
| HVAC-Rough | 8/12/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 8/12/2024 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/23/2024 | Partial Approval | MATTHEW NELSON |
| Green Building Rough | 8/23/2024 | Approved | MATTHEW NELSON |
| Shower Pan | 8/23/2024 | Approved | MATTHEW NELSON |
| Insulation | 8/29/2024 | Corrections Issued | MATTHEW NELSON |
| Interior/Exterior Lathing | 8/29/2024 | Partial Approval | MATTHEW NELSON |
| Insulation | 9/3/2024 | Approved | MATTHEW NELSON |
| Drywall Nailing | 9/10/2024 | Approved | GAREN HAYRAPETYAN |
| Underground Mechanical | 9/19/2024 | Partial Approval | MATTHEW NELSON |
| Underground Mechanical | 9/20/2024 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/17/2024 | Partial Approval | MATTHEW NELSON |
| Final | 10/17/2024 | Partial Inspection | MATTHEW NELSON |
| Green Building Final | 10/17/2024 | Partial Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 10/17/2024 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 10/17/2024 | Partial Inspection | MATTHEW NELSON |
| Smoke Detectors | 10/17/2024 | Partial Inspection | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 10/17/2024 | Partial Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 11/25/2024 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 11/25/2024 | Corrections Issued | RAUL OLAGI |
| Final | 11/25/2024 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 11/25/2024 | Approved | RAUL OLAGI |
| HVAC-Final | 11/25/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 11/25/2024 | Approved | RAUL OLAGI |
| Smoke Detectors | 11/25/2024 | Approved | RAUL OLAGI |
| Verify Sprinkler Sign Off | 11/25/2024 | Approved | RAUL OLAGI |
| Final | 12/17/2024 | Corrections Issued | MATTHEW NELSON |
| Service/Power Release | 12/17/2024 | Corrections Issued | MATTHEW NELSON |
| Final | 12/20/2024 | OK to Issue CofO | MATTHEW NELSON |
| Service/Power Release | 12/20/2024 | Approved | MATTHEW NELSON |