- Permit Issued
- Issued on 8/29/2024
- Issuing Office
- Current Status
- CofO Issued on 6/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2023 | AMY GUEVARRA |
| Corrections Issued | 12/19/2023 | AMY GUEVARRA |
| Applicant returned to address corrections | 3/28/2024 | AMY GUEVARRA |
| Applicant returned to address corrections | 7/12/2024 | AMY GUEVARRA |
| Applicant returned to address corrections | 8/22/2024 | AMY GUEVARRA |
| Plan Check Approved | 8/25/2024 | AMY GUEVARRA |
| Issued | 8/29/2024 | APPLICANT |
| CofO in Progress | 6/1/2026 | JUAN ALVARADO |
| Permit Finaled | 6/3/2026 | JOHN JANSON |
| CofO Issued | 6/3/2026 | JOHN JANSON |
| Permit Finaled | 6/3/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/4/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/18/2024 | EDGAR ALCARAZ |
| Flood clearance | Cleared | 1/18/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 1/18/2024 | EDGAR ALCARAZ |
| Construction within easement | Cleared | 4/27/2024 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 7/25/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 8/20/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Cali Remodeling; Lic. No.: 1061730-B | , |
| Contractor | G E J Construction Inc; Lic. No.: 1061730-B | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/23/2024 | Partial Approval | JEFFREY BULL |
| Footing/Foundation/Slab | 11/1/2024 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2024 | Approved | ARUTYUN MADATYAN |
| Verify Sprinkler Sign Off | 11/22/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 12/6/2024 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 12/6/2024 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 12/6/2024 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 12/6/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 12/6/2024 | Partial Approval | ARUTYUN MADATYAN |
| PLUMBING-Rough | 12/6/2024 | Approved | ARUTYUN MADATYAN |
| Insulation | 12/12/2024 | Conditional Approval | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 12/12/2024 | Partial Approval | GEVORK IPCHYAN |
| Drywall Nailing | 12/20/2024 | Approved | SCOTT SOBEL |
| Insulation | 12/20/2024 | Approved | SCOTT SOBEL |
| SGSOV-Seismic Gas S/O Valve | 4/1/2025 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Service/Power Release | 4/1/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 4/1/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 4/21/2025 | Corrections Issued | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 4/21/2025 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Service/Power Release | 4/21/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 4/21/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| Final | 5/16/2025 | Corrections Issued | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 5/16/2025 | SGSOV Not Ready | JUAN ALVARADO |
| Service/Power Release | 5/16/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Smoke Detectors | 5/16/2025 | Approved | JUAN ALVARADO |
| Final | 6/3/2025 | Corrections Issued | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 6/3/2025 | SGSOV Not Ready | JUAN ALVARADO |
| Service/Power Release | 6/3/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Final | 7/11/2025 | Corrections Issued | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 7/11/2025 | SGSOV Approved | JUAN ALVARADO |
| Service/Power Release | 7/11/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Final | 9/22/2025 | Corrections Issued | JUAN ALVARADO |
| Service/Power Release | 9/22/2025 | Approved | JUAN ALVARADO |
| Final | 5/18/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 5/27/2026 | Approved | JUAN ALVARADO |
| Final | 5/27/2026 | OK to Issue CofO | JUAN ALVARADO |
| HVAC-Final | 5/27/2026 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 5/27/2026 | Approved | JUAN ALVARADO |