6929-6931 N DE CELIS PL 91406

Certificate Information: 6929-6931 N DE CELIS PL 91406

Application / Permit
23010-20000-04970
Plan Check / Job No.
B23VN16960
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
*EPLAN* 108' X 52' ONE STORY DUPLEX PER SB9; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 6/4/2025
Issuing Office
Current Status
Issued on 6/4/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/11/2023 APPLICANT
Assigned to Plan Check Engineer 1/4/2024 SELLA BENYAMIN
Corrections Issued 1/9/2024 SELLA BENYAMIN
Quality Review Completed 1/10/2024 STEVEN KIM
Applicant returned to address corrections 12/20/2024 SELLA BENYAMIN
Plan Check Approved 2/19/2025 SELLA BENYAMIN
Plan Check Approved 4/26/2025 SELLA BENYAMIN
Issued 6/4/2025 APPLICANT

Permit Application Clearance Information

Trees in Parkway Cleared 5/13/2024 ADALBERTO VERA
Miscellaneous Cleared 8/22/2024 NATHAN ROMINE
Senate Bill 9 Cleared 8/22/2024 NATHAN ROMINE
Low Impact Development (LID) Cleared 10/14/2024 JORGE MEJIA LEMUS
Address approval Cleared 10/17/2024 RYAN CASTRO
Hydrant and Access approval Cleared 10/22/2024 JERRY KAO
Eng Process Fee Ord 176,300 Cleared 10/23/2024 RYAN CASTRO
Permit Cleared 10/23/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 10/23/2024 RYAN CASTRO
Sewer availability Cleared 10/23/2024 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Medina,, Ferdinand Casaclang; Lic. No.: C88007 1051 S HOLT AVE APT F      LOS ANGELES, CA 90035

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/5/2025 Partial Inspection GAREN HAYRAPETYAN
PLUMBING-Rough 1/22/2026 Partial Approval OGANES TARAKHCHYAN
Sewer 1/22/2026 Approved OGANES TARAKHCHYAN
Special/Order Compliance 1/26/2026 Corrections Issued RAUL OLAGI
Underground Mechanical 1/26/2026 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 1/28/2026 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 3/5/2026 Conditional Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 3/19/2026 Conditional Approval KIRK SANDERS
Deputy Wood Construction 4/7/2026 Conditional Approval JOSE AVILA
ELECTRICAL-Rough 4/10/2026 Corrections Issued MICHEL ABAJAN
HVAC-Rough 4/14/2026 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 4/15/2026 Approved MICHAEL CORTEZ
Floor/Roof Diaphrgm/Shear Wall 4/17/2026 Conditional Approval KIRK SANDERS
Special/Order Compliance 4/17/2026 Corrections Issued KIRK SANDERS
HVAC-Rough 4/22/2026 Approved MICHAEL CORTEZ
BUILDING-Rough-Frame 4/24/2026 Corrections Issued RAUL OLAGI
Verify Sprinkler Sign Off 4/24/2026 Approved RAUL OLAGI
BUILDING-Rough-Frame 5/4/2026 Conditional Approval KIRK SANDERS
Interior/Exterior Lathing 5/4/2026 Partial Approval KIRK SANDERS
Insulation 5/14/2026 Corrections Issued MICHAEL CORTEZ
Insulation 5/19/2026 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 5/26/2026 Approved MICHAEL CORTEZ
Shower Pan 5/26/2026 Approved MICHAEL CORTEZ
Drywall Nailing 6/2/2026 Approved MICHAEL CORTEZ