8115 N WHEATLAND AVE 91352
Certificate Information: 8115 N WHEATLAND AVE 91352
- Application / Permit
- 23010-20000-04962
- Plan Check / Job No.
- B23VN16949
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 32'-6" x 49' SFD per SB9 Two-Unit Development Ca Govt Code 65852.21 W/ 1'-6" X 7'-10" PORCH. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/16/2025
- Issuing Office
- Current Status
- Issued on 4/16/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/21/2023 | RAPHAEL ROSAS |
| Corrections Issued | 12/28/2023 | RAPHAEL ROSAS |
| Quality Review Completed | 12/29/2023 | STEVEN KIM |
| Building Plans Picked Up | 12/29/2023 | APPLICANT |
| Plan Check Approved | 4/16/2025 | RAPHAEL ROSAS |
| Issued | 4/16/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/4/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 2/8/2024 | CARLOS RAMIREZ |
| Hydrant and Access approval | Cleared | 2/9/2024 | MATTHEW CRAIG |
| Senate Bill 9 | Cleared | 4/3/2024 | ALEX VELA |
| Low Impact Development (LID) | Cleared | 4/8/2025 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 4/8/2025 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Interior/Exterior Lathing | 6/11/2026 Time Frame: 11-1 |
Inspection Request History
| Footing/Foundation/Slab | 1/21/2026 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 1/21/2026 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 1/23/2026 | Corrections Issued | DAVID ANDERSON |
| Special/Order Compliance | 1/23/2026 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 1/27/2026 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 2/6/2026 | Partial Approval | DAVID ANDERSON |
| Footing/Foundation/Slab | 2/20/2026 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 2/24/2026 | Approved | NICHOLAS TROWBRIDGE |
| Wood Frame | 5/1/2026 | Partial Inspection | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2026 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 6/8/2026 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 6/8/2026 | Approved | DAVID ANDERSON |
| Green Building Rough | 6/8/2026 | Approved | DAVID ANDERSON |
| HVAC-Rough | 6/8/2026 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 6/8/2026 | Approved | DAVID ANDERSON |
| Shower Pan | 6/8/2026 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 6/8/2026 | Approved | DAVID ANDERSON |