20138 W CLARK ST 91367

Certificate Information: 20138 W CLARK ST 91367

Application / Permit
23010-20000-04900
Plan Check / Job No.
B23VN16763
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 23'-9" X 21'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK PER WFPP.
Permit Issued
Issued on 12/20/2023
Issuing Office
Current Status
CofO Issued on 3/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/7/2023 APPLICANT
Assigned to Plan Check Engineer 12/8/2023 ARTIN ZARUKIAN
Corrections Issued 12/9/2023 ARTIN ZARUKIAN
Building Plans Picked Up 12/11/2023 APPLICANT
Plan Check Approved 12/20/2023 ROSENDO MEDINA
Issued 12/20/2023 APPLICANT
CofO in Progress 2/18/2025 ALEXANDER HANDY
Permit Finaled 3/19/2025 JOHN JANSON
CofO Issued 3/19/2025 JOHN JANSON
Permit Finaled 3/19/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 12/11/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/11/2023 CARLOS AGUILERA
Sewer availability Cleared 12/11/2023 CARLOS AGUILERA
Construction near power lines Cleared 12/13/2023 WALTER RAMIREZ
Low Impact Development (LID) Cleared 12/19/2023 ROGELIO CORTES
Grading Pre-Inspection Cleared 12/20/2023 BRIAN MILLER
Roof/Waste drainage to street Cleared 12/20/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/19/2024 Partial Approval ALEXANDER HANDY
Sewer 1/19/2024 Approved ALEXANDER HANDY
Excavation/Setback/Form/Re-Bar 1/25/2024 Corrections Issued ALEXANDER HANDY
Excavation/Setback/Form/Re-Bar 2/26/2024 Corrections Issued ARUTYUN MADATYAN
Excavation/Setback/Form/Re-Bar 2/29/2024 Corrections Issued ARUTYUN MADATYAN
Excavation/Setback/Form/Re-Bar 3/15/2024 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 4/5/2024 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Rough 4/5/2024 Not Ready for Inspection ARUTYUN MADATYAN
Green Building Rough 4/5/2024 Not Ready for Inspection ARUTYUN MADATYAN
MERV13>=Rough 4/5/2024 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 4/5/2024 Not Ready for Inspection ARUTYUN MADATYAN
Verify Sprinkler Sign Off 4/5/2024 Not Ready for Inspection ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 4/9/2024 Approved ARUTYUN MADATYAN
ELECTRICAL-Rough 4/10/2024 Partial Approval ARUTYUN MADATYAN
PLUMBING-Rough 4/10/2024 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 5/2/2024 No Access for Inspection ARUTYUN MADATYAN
Green Building Rough 5/2/2024 No Access for Inspection ARUTYUN MADATYAN
MERV13>=Rough 5/2/2024 No Access for Inspection ARUTYUN MADATYAN
Rough-Elec/Plmb/HVAC 5/2/2024 No Access for Inspection ARUTYUN MADATYAN
Verify Sprinkler Sign Off 5/2/2024 No Access for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 5/3/2024 Corrections Issued ARUTYUN MADATYAN
Rough-Elec/Plmb/HVAC 5/3/2024 Approved ARUTYUN MADATYAN
Insulation 5/8/2024 Approved ARUTYUN MADATYAN
Drywall Nailing 5/16/2024 Approved ARUTYUN MADATYAN
Green Building Rough 5/16/2024 Approved ARUTYUN MADATYAN
Shower Pan 5/31/2024 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 6/5/2024 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 7/15/2024 Approved ARUTYUN MADATYAN
Final 7/15/2024 Corrections Issued ARUTYUN MADATYAN
Footing/Foundation/Slab 7/15/2024 Approved ARUTYUN MADATYAN
Green Building Final 7/15/2024 No Access for Inspection ARUTYUN MADATYAN
MERV13>=Final 7/15/2024 Approved ARUTYUN MADATYAN
MERV13>=Rough 7/15/2024 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 7/15/2024 SGSOV Not Ready ARUTYUN MADATYAN
Service/Power Release 7/15/2024 Not Ready for Inspection ARUTYUN MADATYAN
Smoke Detectors 7/15/2024 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 7/30/2024 SGSOV Not Ready ARUTYUN MADATYAN
Final 8/2/2024 Not Ready for Inspection ARUTYUN MADATYAN
Green Building Final 8/2/2024 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 8/2/2024 SGSOV Approved ARUTYUN MADATYAN
Service/Power Release 8/2/2024 Not Ready for Inspection ARUTYUN MADATYAN
Final 10/17/2024 Not Ready for Inspection ARUTYUN MADATYAN
Green Building Final 10/17/2024 Not Ready for Inspection ARUTYUN MADATYAN
Service/Power Release 10/17/2024 Not Ready for Inspection ARUTYUN MADATYAN
Final 12/13/2024 Not Ready for Inspection JEFFREY HARTLINE
Green Building Final 12/13/2024 Not Ready for Inspection JEFFREY HARTLINE
Service/Power Release 12/13/2024 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Final 2/14/2025 Approved ALEXANDER HANDY
Final 2/14/2025 OK to Issue CofO ALEXANDER HANDY
Green Building Final 2/14/2025 Approved ALEXANDER HANDY
HVAC-Final 2/14/2025 Approved ALEXANDER HANDY
PLUMBING-Final 2/14/2025 Approved ALEXANDER HANDY
Service/Power Release 2/14/2025 Approved ALEXANDER HANDY