10162 N MCCLEMONT AVE 91042
Certificate Information: 10162 N MCCLEMONT AVE 91042
- Application / Permit
- 23010-20000-04882
- Plan Check / Job No.
- B23VN16667
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- NEW 20'-2" x 27'-4" TWO-STORY ACCESSORY LIVING QUARTERS; NFPA-13D THRU-OUT
- Permit Issued
- Issued on 4/16/2024
- Issuing Office
- Current Status
- CofO Issued on 3/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/28/2023 | SEAN SHAHMIRI |
| Corrections Issued | 1/2/2024 | SEAN SHAHMIRI |
| Quality Review Completed | 1/4/2024 | STEVEN KIM |
| Applicant returned to address corrections | 2/2/2024 | SEAN SHAHMIRI |
| Plan Check Approved | 4/16/2024 | SEAN SHAHMIRI |
| Issued | 4/16/2024 | APPLICANT |
| CofO in Progress | 3/13/2025 | WILLIAM WREN |
| Permit Finaled | 3/25/2025 | RUBEN SALAS |
| CofO Issued | 3/25/2025 | RUBEN SALAS |
| Permit Finaled | 3/25/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/7/2024 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 2/8/2024 | CHARLES POWELL |
| Hydrant and Access approval | Cleared | 3/12/2024 | RUEL COLE |
| Low Impact Development (LID) | Cleared | 3/22/2024 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 3/26/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/6/2024 | Partial Approval | WILLIAM WREN |
| Sewer | 5/6/2024 | Not Ready for Inspection | WILLIAM WREN |
| Excavation/Setback/Form/Re-Bar | 5/7/2024 | Corrections Issued | WILLIAM WREN |
| Excavation/Setback/Form/Re-Bar | 5/9/2024 | Corrections Issued | WILLIAM WREN |
| Excavation/Setback/Form/Re-Bar | 5/15/2024 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2024 | Partial Approval | MATTHEW NELSON |
| Wood Frame | 5/24/2024 | Corrections Issued | MATTHEW NELSON |
| Deputy Wood Construction | 7/12/2024 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 7/12/2024 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2024 | Approved | WILLIAM WREN |
| HVAC-Rough | 7/12/2024 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 7/12/2024 | Not Ready for Inspection | WILLIAM WREN |
| BUILDING-Rough-Frame | 7/16/2024 | No Access for Inspection | WILLIAM WREN |
| PLUMBING-Rough | 7/16/2024 | Approved | WILLIAM WREN |
| Insulation | 8/1/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 8/1/2024 | Partial Approval | MATTHEW NELSON |
| Drywall Nailing | 8/7/2024 | Corrections Issued | WILLIAM WREN |
| Green Building Rough | 8/7/2024 | Approved | WILLIAM WREN |
| Shower Pan | 8/7/2024 | Approved | WILLIAM WREN |
| Drywall Nailing | 8/12/2024 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 8/19/2024 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/5/2025 | Approved | WILLIAM WREN |
| Final | 3/5/2025 | OK to Issue CofO | WILLIAM WREN |
| Footing/Foundation/Slab | 3/5/2025 | Approved | WILLIAM WREN |
| Green Building Final | 3/5/2025 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 3/5/2025 | SGSOV Not Required | WILLIAM WREN |
| Smoke Detectors | 3/5/2025 | Approved | WILLIAM WREN |
| Verify Sprinkler Sign Off | 3/5/2025 | Approved | WILLIAM WREN |