14950 W TUBA ST 91345

Certificate Information: 14950 W TUBA ST 91345

Application / Permit
23010-20000-04879
Plan Check / Job No.
B23VN16658
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**ePlan** Convert (E) Detached Garage to (N) ADU with addition per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 5/18/2024
Issuing Office
Current Status
CofO Issued on 9/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/7/2023 APPLICANT
Assigned to Plan Check Engineer 12/12/2023 EDWIN ESPIN
Corrections Issued 12/13/2023 EDWIN ESPIN
Applicant returned to address corrections 12/19/2023 AMY GUEVARRA
Applicant returned to address corrections 1/10/2024 AMY GUEVARRA
Plan Check Approved 5/18/2024 EDWIN ESPIN
Issued 5/18/2024 APPLICANT
CofO in Progress 9/12/2025 JENNIFER RABUCHIN
Permit Finaled 9/19/2025 RUBEN SALAS
CofO Issued 9/19/2025 RUBEN SALAS
Permit Finaled 9/19/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/29/2023 EDGAR ALCARAZ
Sewer availability Cleared 12/29/2023 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 1/2/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 1/13/2024 JOHN LIN
Construction near power lines Cleared 5/8/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Bogossian,, Oshin; Lic. No.: C78191 6518 GREELEY ST      TUJUNGA, CA 91042

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/7/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 4/22/2025 Approved NICHOLAS TROWBRIDGE
Sewer 4/22/2025 Approved NICHOLAS TROWBRIDGE
Underground Mechanical 4/22/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 5/9/2025 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 5/9/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 5/9/2025 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 5/9/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 5/9/2025 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/19/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 5/19/2025 Approved JENNIFER RABUCHIN
Green Building Rough 5/19/2025 Approved JENNIFER RABUCHIN
HVAC-Rough 5/19/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 5/19/2025 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 5/19/2025 Approved JENNIFER RABUCHIN
Insulation 5/22/2025 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/28/2025 Approved JENNIFER RABUCHIN
Drywall Nailing 6/3/2025 Approved JENNIFER RABUCHIN
Shower Pan 6/3/2025 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 6/10/2025 Approved JENNIFER RABUCHIN
Shower Pan 6/10/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/28/2025 Approved JENNIFER RABUCHIN
Final 8/28/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Final 8/28/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 8/28/2025 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 8/28/2025 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 8/28/2025 Approved JENNIFER RABUCHIN
Final 9/11/2025 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 9/11/2025 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 9/11/2025 SGSOV Approved JENNIFER RABUCHIN
HVAC-Final 9/12/2025 Approved JENNIFER RABUCHIN