10246 N BOTHWELL ROAD 91324

Certificate Information: 10246 N BOTHWELL ROAD 91324

Application / Permit
23010-20000-04877
Plan Check / Job No.
B23VN16653
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
Eplan: New Detached 1-Story Recreation Room
Permit Issued
Issued on 2/20/2024
Issuing Office
Current Status
CofO Issued on 10/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/5/2023 APPLICANT
Assigned to Plan Check Engineer 12/8/2023 DAVID CASTILLO
Corrections Issued 12/12/2023 DAVID CASTILLO
Applicant returned to address corrections 12/21/2023 AMY GUEVARRA
Plan Check Approved 12/28/2023 AMY GUEVARRA
Issued 2/20/2024 APPLICANT
CofO in Progress 7/8/2024 KRISTEN BEVERIDGE
Permit Finaled 10/18/2024 JOHN JANSON
CofO Issued 10/18/2024 JOHN JANSON
Permit Finaled 10/18/2024 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/18/2023 CARLOS RAMIREZ
Sewer availability Cleared 12/18/2023 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 12/19/2023 CARLOS RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: NA78215       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/21/2024 Approved DAVID SCANTLIN
Footing/Foundation/Slab 3/21/2024 Approved DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 3/21/2024 Not Ready for Inspection DAVID SCANTLIN
Underground Mechanical 3/21/2024 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 3/28/2024 Not Ready for Inspection DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 3/28/2024 Approved DAVID SCANTLIN
Green Building Rough 3/28/2024 Not Ready for Inspection DAVID SCANTLIN
Verify Sprinkler Sign Off 3/28/2024 Not Ready for Inspection DAVID SCANTLIN
Wood Frame 3/28/2024 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 4/29/2024 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 4/29/2024 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 4/29/2024 Partial Approval ARUTYUN MADATYAN
Sewer 4/29/2024 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 5/10/2024 Approved DAVID SCANTLIN
Green Building Rough 5/10/2024 Approved DAVID SCANTLIN
HVAC-Rough 5/10/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 5/10/2024 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 5/10/2024 Approved DAVID SCANTLIN
Drywall Nailing 5/21/2024 Approved DAVID SCANTLIN
ELECTRICAL-Final 7/5/2024 Approved KRISTEN CAUSEY
Final 7/5/2024 OK to Issue CofO KRISTEN CAUSEY
Green Building Final 7/5/2024 Approved KRISTEN CAUSEY
HVAC-Final 7/5/2024 Approved KRISTEN CAUSEY
PLUMBING-Final 7/5/2024 Approved KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 7/5/2024 SGSOV Approved KRISTEN CAUSEY
Service/Power Release 7/5/2024 Approved KRISTEN CAUSEY
Smoke Detectors 7/5/2024 Approved KRISTEN CAUSEY