11618 N BALBOA BLVD 91344
Certificate Information: 11618 N BALBOA BLVD 91344
- Application / Permit
- 23010-20000-04824
- Plan Check / Job No.
- B23VN16502
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 27' 1" x 20' two story ADU per LAMC 12.22 A.33 (c)-(d), all work done per engineer.
- Permit Issued
- Issued on 12/20/2024
- Issuing Office
- Current Status
- CofO Issued on 5/14/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/7/2023 | NAREG ATARIAN |
| Corrections Issued | 12/9/2023 | NAREG ATARIAN |
| Quality Review Completed | 12/12/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 12/14/2023 | APPLICANT |
| Plan Check Approved | 8/12/2024 | NAREG ATARIAN |
| Issued | 12/20/2024 | APPLICANT |
| CofO in Progress | 4/3/2026 | CHRISTOPHER ROJAS |
| Permit Finaled | 5/14/2026 | RUBEN SALAS |
| CofO Issued | 5/14/2026 | RUBEN SALAS |
| Permit Finaled | 5/14/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/5/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/6/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/6/2024 | CARLOS AGUILERA |
| Senate Bill 9 | Cleared | 2/8/2024 | BRENNEN OBETO |
| Miscellaneous | Cleared | 2/13/2024 | GREGORIO GUILLERMO |
| Low Impact Development (LID) | Cleared | 6/12/2024 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 6/12/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 7/17/2024 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 8/12/2024 | GERMAN RODRIGUEZ MENDOZA |
| Grading Pre-Inspection | Cleared | 8/12/2024 | GERMAN RODRIGUEZ MENDOZA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Andrejic,, Milos; Lic. No.: C67443 | 3601 BEVERLY RIDGE DR SHERMAN OAKS, CA 91423 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/15/2025 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 1/28/2025 | Conditional Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2025 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 2/26/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/1/2025 | No Access for Inspection | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2025 | No Access for Inspection | CHRISTOPHER ROJAS |
| Green Building Rough | 4/1/2025 | No Access for Inspection | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 4/1/2025 | No Access for Inspection | CHRISTOPHER ROJAS |
| Pre-Inspection | 4/4/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Green Building Rough | 4/8/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 4/8/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 4/17/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 4/17/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 4/17/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Special/Order Compliance | 4/23/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 4/29/2025 | Corrections Issued | RAUL OLAGI |
| Special/Order Compliance | 4/29/2025 | Corrections Issued | RAUL OLAGI |
| Underground Mechanical | 4/29/2025 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 5/1/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2025 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 5/7/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 5/7/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 5/7/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 5/7/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 5/14/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 5/14/2025 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 5/14/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 5/22/2025 | Approved | CHRISTOPHER ROJAS |
| Insulation | 5/22/2025 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 6/2/2025 | Approved | LOUIS ESCOTO |
| Shower Pan | 6/11/2025 | No Access for Inspection | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 6/13/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Shower Pan | 6/13/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 6/17/2025 | Approved | CHRISTOPHER ROJAS |
| Sewer | 6/25/2025 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 10/1/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 10/1/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 10/1/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Final | 10/1/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Final | 10/1/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Service/Power Release | 10/1/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 10/1/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 1/7/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 1/7/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Service/Power Release | 1/7/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 4/2/2026 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Green Building Final | 4/2/2026 | Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 4/2/2026 | Approved | CHRISTOPHER ROJAS |