9905 N ALDEA AVE 91325

Certificate Information: 9905 N ALDEA AVE 91325

Application / Permit
23010-20000-04823
Plan Check / Job No.
B23VN16497
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan N 2-STORY SB 9 UNIT PER GCS 65852.21. TO BE FULLY SPRINKLERED NFPA 13D
Permit Issued
Issued on 7/11/2024
Issuing Office
Current Status
Issued on 7/11/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/5/2023 APPLICANT
Assigned to Plan Check Engineer 12/21/2023 MARCELA FRANQUEZ
Corrections Issued 1/5/2024 MARCELA FRANQUEZ
Quality Review Completed 1/10/2024 GARO TELMI
Applicant returned to address corrections 4/8/2024 MARCELA FRANQUEZ
Applicant returned to address corrections 5/10/2024 MARCELA FRANQUEZ
Plan Check Approved 6/20/2024 MARCELA FRANQUEZ
Issued 7/11/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/18/2024 NIKKI ZULUETA
Senate Bill 9 Cleared 1/23/2024 ASHLEY RODARTE
Sewer availability Cleared 1/24/2024 NIKKI ZULUETA
Low Impact Development (LID) Cleared 4/17/2024 TOMMY YIN
Roof/Waste drainage to street Cleared 4/26/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/1/2024 CARLOS RAMIREZ
GPI Written Notices Cleared 6/13/2024 MARCELA FRANQUEZ
Grading Pre-Inspection Cleared 6/13/2024 MARCELA FRANQUEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 11/27/2024 Approved JAVIER RAMOS JR
Underground Mechanical 11/27/2024 Partial Approval JAVIER RAMOS JR
Pre-Inspection 12/31/2024 Approved JAVIER RAMOS JR
Underground Mechanical 12/31/2024 Partial Approval JAVIER RAMOS JR
Underground Mechanical 4/18/2025 No Access for Inspection CHRISTOPHER ROJAS
Underground Mechanical 4/22/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 4/24/2025 Corrections Issued CHRISTOPHER ROJAS
Underground Mechanical 4/24/2025 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 6/16/2025 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 9/18/2025 Corrections Issued NICHOLAS TROWBRIDGE
Wood Frame 9/18/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 9/19/2025 Partial Approval NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 10/8/2025 Corrections Issued NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 10/16/2025 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 10/24/2025 Approved NICHOLAS TROWBRIDGE
Green Building Rough 10/24/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 11/6/2025 Partial Approval MICHAEL CORTEZ
ELECTRICAL-Rough 11/12/2025 Corrections Issued NICHOLAS TROWBRIDGE
PLUMBING-Rough 11/12/2025 Corrections Issued NICHOLAS TROWBRIDGE
Verify Sprinkler Sign Off 11/12/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 12/18/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 12/18/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 12/18/2025 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 12/18/2025 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 12/18/2025 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 12/24/2025 Approved KEVIN BERBERYAN
Green Building Rough 12/24/2025 Approved KEVIN BERBERYAN
Rough-Elec/Plmb/HVAC 12/24/2025 Approved KEVIN BERBERYAN
Insulation 1/6/2026 Corrections Issued CHRISTOPHER ROJAS
Drywall Nailing 1/16/2026 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 1/16/2026 Approved MICHAEL CORTEZ
Sewer 2/13/2026 Approved MICHAEL CORTEZ
Shower Pan 2/13/2026 Approved MICHAEL CORTEZ