9905 N ALDEA AVE 91325
Certificate Information: 9905 N ALDEA AVE 91325
- Application / Permit
- 23010-20000-04823
- Plan Check / Job No.
- B23VN16497
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan N 2-STORY SB 9 UNIT PER GCS 65852.21. TO BE FULLY SPRINKLERED NFPA 13D
- Permit Issued
- Issued on 7/11/2024
- Issuing Office
- Current Status
- Issued on 7/11/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/21/2023 | MARCELA FRANQUEZ |
| Corrections Issued | 1/5/2024 | MARCELA FRANQUEZ |
| Quality Review Completed | 1/10/2024 | GARO TELMI |
| Applicant returned to address corrections | 4/8/2024 | MARCELA FRANQUEZ |
| Applicant returned to address corrections | 5/10/2024 | MARCELA FRANQUEZ |
| Plan Check Approved | 6/20/2024 | MARCELA FRANQUEZ |
| Issued | 7/11/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/18/2024 | NIKKI ZULUETA |
| Senate Bill 9 | Cleared | 1/23/2024 | ASHLEY RODARTE |
| Sewer availability | Cleared | 1/24/2024 | NIKKI ZULUETA |
| Low Impact Development (LID) | Cleared | 4/17/2024 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 4/26/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/1/2024 | CARLOS RAMIREZ |
| GPI Written Notices | Cleared | 6/13/2024 | MARCELA FRANQUEZ |
| Grading Pre-Inspection | Cleared | 6/13/2024 | MARCELA FRANQUEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 11/27/2024 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 11/27/2024 | Partial Approval | JAVIER RAMOS JR |
| Pre-Inspection | 12/31/2024 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 12/31/2024 | Partial Approval | JAVIER RAMOS JR |
| Underground Mechanical | 4/18/2025 | No Access for Inspection | CHRISTOPHER ROJAS |
| Underground Mechanical | 4/22/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 4/24/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Underground Mechanical | 4/24/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 6/16/2025 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Wood Frame | 9/18/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2025 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2025 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 10/24/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 11/6/2025 | Partial Approval | MICHAEL CORTEZ |
| ELECTRICAL-Rough | 11/12/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 11/12/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 11/12/2025 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 12/18/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 12/18/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 12/18/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Rough | 12/18/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 12/18/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 12/24/2025 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 12/24/2025 | Approved | KEVIN BERBERYAN |
| Rough-Elec/Plmb/HVAC | 12/24/2025 | Approved | KEVIN BERBERYAN |
| Insulation | 1/6/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Drywall Nailing | 1/16/2026 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 1/16/2026 | Approved | MICHAEL CORTEZ |
| Sewer | 2/13/2026 | Approved | MICHAEL CORTEZ |
| Shower Pan | 2/13/2026 | Approved | MICHAEL CORTEZ |