11411 W COHASSET ST 91605
Certificate Information: 11411 W COHASSET ST 91605
- Application / Permit
- 23010-20000-04815
- Plan Check / Job No.
- B23VN16455
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW IRR. SHAPED 25' X 41'-7" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 2/23/2024
- Issuing Office
- Current Status
- CofO Issued on 10/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/4/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 12/5/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 12/7/2023 | APPLICANT |
| Applicant returned to address corrections | 2/15/2024 | ANGELICA DAVE |
| Issued | 2/23/2024 | APPLICANT |
| CofO in Progress | 9/30/2024 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 10/21/2024 | DANIEL ORRANTE |
| CofO Issued | 10/21/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/21/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/6/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 12/7/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 12/7/2023 | LEE GUILBEAUX |
| Low Impact Development (LID) | Cleared | 12/13/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 1/4/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 1/4/2024 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/5/2024 | Not Ready for Inspection | DAVID MATSON |
| Underground Mechanical | 4/9/2024 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 4/11/2024 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 4/15/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Underground Mechanical | 4/17/2024 | Partial Approval | JOHN HAYES |
| Footing/Foundation/Slab | 4/24/2024 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 4/24/2024 | Partial Approval | JOHN HAYES |
| Footing/Foundation/Slab | 4/26/2024 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 6/27/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 7/1/2024 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 7/1/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 7/5/2024 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2024 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 7/5/2024 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 7/5/2024 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 7/9/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 7/11/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 7/11/2024 | Approved | JOSE AVILA |
| Green Building Rough | 7/11/2024 | Approved | JOSE AVILA |
| Insulation | 7/17/2024 | Approved | KEVIN BERBERYAN |
| Shower Pan | 7/17/2024 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 7/22/2024 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 8/7/2024 | Approved | MISAEL ESPARZA |
| Service/Power Release | 8/23/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 8/26/2024 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 9/4/2024 | Approved | JOSE AVILA |
| Final | 9/4/2024 | Corrections Issued | JOSE AVILA |
| Green Building Final | 9/4/2024 | Approved | JOSE AVILA |
| Smoke Detectors | 9/4/2024 | Approved | JOSE AVILA |
| Final | 9/10/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 9/10/2024 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 9/10/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 9/27/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 9/27/2024 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 9/27/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 9/27/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 9/27/2024 | Approved | ROBERTO PALACIOS-LOPEZ |