4455-4457 N KATHERINE AVE 91423

Certificate Information: 4455-4457 N KATHERINE AVE 91423

Application / Permit
23010-20000-04782
Plan Check / Job No.
B23VN16329
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
***DEMO PERMIT MUST BE WITHDRAWN*** MAJOR MODEL & ADDITION TO MAKE A 71'6"X32'0" 2-STORY SINGLE FAMILY DWELLING WITH AN ATTACHED 2-CAR GARAGE AND AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) NFPA 13 D FIRE SPRINKLERS REQUIRED THROGUHOUT. (1 OF 3)
Permit Issued
Issued on 4/15/2024
Issuing Office
Current Status
CofO Issued on 4/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/29/2023 APPLICANT
Assigned to Plan Check Engineer 12/7/2023 MARVEL DELACRUZ
Corrections Issued 12/14/2023 MARVEL DELACRUZ
Quality Review Completed 12/15/2023 OMID HEDAYAT
Building Plans Picked Up 12/21/2023 APPLICANT
Applicant returned to address corrections 4/2/2024 MARVEL DELACRUZ
Plan Check Approved 4/12/2024 MARVEL DELACRUZ
Issued 4/15/2024 APPLICANT
CofO in Progress 4/9/2025 JOSE AVILA
Permit Finaled 4/24/2025 RUBEN SALAS
CofO Issued 4/24/2025 RUBEN SALAS
Permit Finaled 4/24/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/16/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/18/2023 CARLOS AGUILERA
Sewer availability Cleared 12/18/2023 CARLOS AGUILERA
ZI Cleared 12/19/2023 MAYELA VILLA
Trees in Parkway Cleared 1/18/2024 ADALBERTO VERA
Hydrant and Access approval Cleared 2/3/2024 RUEL COLE
Low Impact Development (LID) Cleared 3/27/2024 SAMUEL LINN
Permit Cleared 4/1/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 4/1/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

DANIEL ORRANTE, (818) 374-1157 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/10/2024 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 5/10/2024 Partial Approval MISAEL ESPARZA
Sewer 5/10/2024 Approved MISAEL ESPARZA
Deputy Drilled-In Anchors 5/16/2024 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 5/16/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 5/21/2024 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 5/28/2024 Conditional Approval MISAEL ESPARZA
Deputy Wood Construction 6/10/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 6/10/2024 Partial Approval MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 6/27/2024 Partial Approval JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 7/10/2024 Corrections Issued MISAEL ESPARZA
HVAC-Rough 8/7/2024 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 8/7/2024 Approved MISAEL ESPARZA
ELECTRICAL-Rough 8/9/2024 Approved MISAEL ESPARZA
Pre-Inspection 8/16/2024 Partial Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/27/2024 Partial Approval JUAN VALENZUELA
BUILDING-Rough-Frame 9/10/2024 Not Ready for Inspection JUAN VALENZUELA
Green Building Rough 9/10/2024 Corrections Issued JUAN VALENZUELA
HVAC-Rough 9/10/2024 Corrections Issued JUAN VALENZUELA
Interior/Exterior Lathing 9/10/2024 Partial Approval JUAN VALENZUELA
MERV13>=Rough 9/10/2024 Approved JUAN VALENZUELA
Shower Pan 9/10/2024 Approved JUAN VALENZUELA
HVAC-Rough 9/24/2024 Approved JUAN VALENZUELA
Interior/Exterior Lathing 9/24/2024 Approved JUAN VALENZUELA
Special/Order Compliance 9/27/2024 Partial Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 10/15/2024 Approved JUAN VALENZUELA
Drywall Nailing 10/15/2024 Approved JUAN VALENZUELA
Green Building Rough 10/15/2024 Approved JUAN VALENZUELA
Insulation 10/15/2024 Approved JUAN VALENZUELA
Verify Sprinkler Sign Off 10/15/2024 Approved JUAN VALENZUELA
ELECTRICAL-Final 3/5/2025 Not Ready for Inspection JUAN VALENZUELA
HVAC-Final 3/5/2025 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Final 3/5/2025 Not Ready for Inspection JUAN VALENZUELA
HVAC-Final 3/14/2025 Corrections Issued JOSE AVILA
MERV13>=Final 3/14/2025 Corrections Issued JOSE AVILA
ELECTRICAL-Final 3/19/2025 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 3/19/2025 Approved JOSE AVILA
Green Building Final 3/19/2025 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 3/19/2025 SGSOV Approved JOSE AVILA
Smoke Detectors 3/19/2025 Approved JOSE AVILA
MERV13>=Final 3/24/2025 Approved JOSE AVILA
PLUMBING-Final 3/24/2025 Approved JOSE AVILA
ELECTRICAL-Final 3/28/2025 Approved JOSE AVILA
Service/Power Release 4/4/2025 Approved JOSE AVILA
Final 4/9/2025 OK to Issue CofO JOSE AVILA