609-609 1/2 W 54TH ST 90037
Certificate Information: 609-609 1/2 W 54TH ST 90037
- Application / Permit
- 23010-20000-04781
- Plan Check / Job No.
- B23VN16312
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ****ePlan**** New 2-story duplex with att. 1-car garage at front and att. 2-car garage at rear
- Permit Issued
- Issued on 7/3/2024
- Issuing Office
- Current Status
- CofO Issued on 12/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2023 | REZA HAGHIGHAT |
| Corrections Issued | 12/1/2023 | REZA HAGHIGHAT |
| Quality Review Completed | 12/5/2023 | KAVIAN REFAHI |
| Applicant returned to address corrections | 5/13/2024 | REZA HAGHIGHAT |
| Plan Check Approved | 5/19/2024 | REZA HAGHIGHAT |
| Issued | 7/3/2024 | APPLICANT |
| CofO in Progress | 12/3/2024 | SABAS ALONSO |
| Permit Finaled | 12/7/2024 | DEROLD HAUFF |
| CofO Issued | 12/7/2024 | DEROLD HAUFF |
| Permit Finaled | 12/7/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/12/2024 | ARNULFO CHAMU |
| Highway dedication | Cleared | 1/12/2024 | ARNULFO CHAMU |
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2024 | ARNULFO CHAMU |
| Sewer availability | Cleared | 1/17/2024 | ARNULFO CHAMU |
| Low Impact Development (LID) | Cleared | 1/25/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 1/25/2024 | ARNULFO CHAMU |
| Hydrant and Access approval | Cleared | 1/26/2024 | LAVEON RIDER |
| CPC | Cleared | 1/29/2024 | RUBEN VASQUEZ |
| SB8 RUD | Cleared | 4/29/2024 | BLAKE BOULIGNY |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/23/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2024 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 7/31/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2024 | Partial Approval | MICHAEL LEWIS |
| Insulation | 8/1/2024 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2024 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2024 | Approved | SABAS ALONSO |
| HVAC-Rough | 9/25/2024 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 9/25/2024 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 9/26/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 9/26/2024 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 9/26/2024 | Approved | SABAS ALONSO |
| Insulation | 9/27/2024 | Approved | SABAS ALONSO |
| Drywall Nailing | 10/17/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 10/17/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 11/15/2024 | Conditional Approval | SABAS ALONSO |
| ELECTRICAL-Final | 11/27/2024 | Approved | SABAS ALONSO |
| Final | 11/27/2024 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Final | 11/27/2024 | Approved | SABAS ALONSO |
| PLUMBING-Final | 11/27/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/27/2024 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 11/27/2024 | Approved | SABAS ALONSO |
| Final | 12/2/2024 | OK to Issue CofO | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/2/2024 | SGSOV No Gas | SABAS ALONSO |
| Service/Power Release | 12/2/2024 | Approved | SABAS ALONSO |