5910-5910 1/2 N MAMMOTH AVE 91401
Certificate Information: 5910-5910 1/2 N MAMMOTH AVE 91401
- Application / Permit
- 23010-20000-04772
- Plan Check / Job No.
- B23VN16275
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EPLAN. NEW 2 STORY DUPLEX (PER SB9, UNDER TWO-UNIT DEVELOPEMENT) -BLDG SPRINKLERED THRU-OUT
- Permit Issued
- Issued on 6/21/2024
- Issuing Office
- Current Status
- CofO in Progress on 7/2/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
Submitted | 11/28/2023 | APPLICANT |
Assigned to Plan Check Engineer | 12/14/2023 | MAHNAZ NOURHASHEMI |
Corrections Issued | 12/22/2023 | MAHNAZ NOURHASHEMI |
Quality Review Completed | 1/4/2024 | TU HUA |
Applicant returned to address corrections | 6/11/2024 | MAHNAZ NOURHASHEMI |
Plan Check Approved | 6/14/2024 | MAHNAZ NOURHASHEMI |
Issued | 6/21/2024 | APPLICANT |
CofO in Progress | 7/2/2025 | RYAN SALAZAR |
Permit Application Clearance Information
Address approval | Cleared | 1/5/2024 | CARLOS AGUILERA |
Eng Process Fee Ord 176,300 | Cleared | 1/5/2024 | CARLOS AGUILERA |
Sewer availability | Cleared | 1/5/2024 | CARLOS AGUILERA |
Senate Bill 9 | Cleared | 1/19/2024 | JAZMIN ROQUE |
Hydrant and Access approval | Cleared | 2/21/2024 | MATTHEW CRAIG |
Low Impact Development (LID) | Cleared | 5/21/2024 | LUIS LUVANO |
Roof/Waste drainage to street | Cleared | 5/28/2024 | MARKOS PEREZ-BRAN |
Contact Information
Contractor | Owner-Builder | , |
Engineer | Gharai,, Armin; Lic. No.: C61464 | 6701 CORIE LN WEST HILLS, CA 91307 |
Inspector Information
RYAN SALAZAR, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Underground Mechanical | 7/23/2024 | Approved | RYAN SALAZAR |
Excavation/Setback/Form/Re-Bar | 7/31/2024 | Approved | VINCENT HANLEY |
Footing/Foundation/Slab | 7/31/2024 | Approved | VINCENT HANLEY |
Sewer | 8/7/2024 | Approved | RYAN SALAZAR |
Floor/Roof Diaphrgm/Shear Wall | 8/21/2024 | Partial Approval | RYAN SALAZAR |
Floor/Roof Diaphrgm/Shear Wall | 10/3/2024 | Partial Approval | RYAN SALAZAR |
PLUMBING-Rough | 10/15/2024 | Approved | RYAN SALAZAR |
HVAC-Rough | 10/23/2024 | Approved | RYAN SALAZAR |
BUILDING-Rough-Frame | 10/28/2024 | Approved | RYAN SALAZAR |
Green Building Rough | 10/28/2024 | Approved | RYAN SALAZAR |
Verify Sprinkler Sign Off | 10/28/2024 | Approved | RYAN SALAZAR |
Insulation | 11/26/2024 | Corrections Issued | KEVIN BERBERYAN |
Insulation | 12/2/2024 | Approved | RYAN SALAZAR |
Drywall Nailing | 12/10/2024 | Approved | JOSE AVILA |
Interior/Exterior Lathing | 12/18/2024 | Corrections Issued | JENNIFER RABUCHIN |
Interior/Exterior Lathing | 12/20/2024 | Partial Approval | RYAN SALAZAR |
Shower Pan | 12/30/2024 | Approved | RYAN SALAZAR |
Interior/Exterior Lathing | 1/23/2025 | Approved | RYAN SALAZAR |
Underground Mechanical | 4/15/2025 | Approved | RYAN SALAZAR |
Final | 5/13/2025 | Corrections Issued | RYAN SALAZAR |
Green Building Final | 5/13/2025 | Approved | RYAN SALAZAR |
SGSOV-Seismic Gas S/O Valve | 5/13/2025 | SGSOV Not Required | RYAN SALAZAR |
Service/Power Release | 5/13/2025 | Not Ready for Inspection | RYAN SALAZAR |
Smoke Detectors | 5/13/2025 | Approved | RYAN SALAZAR |
Final | 6/25/2025 | OK to Issue CofO | RYAN SALAZAR |
Service/Power Release | 6/25/2025 | Approved | RYAN SALAZAR |