112 W 60TH ST 90003
Certificate Information: 112 W 60TH ST 90003
- Application / Permit
- 23010-20000-04762
- Plan Check / Job No.
- B23VN16227
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 4/5/2024
- Issuing Office
- Current Status
- Issued on 4/5/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/6/2023 | PINANK PATEL |
| Corrections Issued | 12/13/2023 | PINANK PATEL |
| Plan Check Approved | 1/24/2024 | ROSENDO MEDINA |
| Issued | 4/5/2024 | APPLICANT |
Permit Application Clearance Information
| Hold | Cleared | 12/13/2023 | MARIA VENDIVIL |
| Address approval | Cleared | 12/22/2023 | TREVOR QUAN |
| CPC | Cleared | 12/22/2023 | ASHLEY RODARTE |
| Eng Process Fee Ord 176,300 | Cleared | 12/26/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 12/26/2023 | TREVOR QUAN |
| Low Impact Development (LID) | Cleared | 1/2/2024 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 1/6/2024 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 1/26/2024 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/16/2024 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 7/2/2024 | Partial Approval | MICHAEL LEWIS |
| Footing/Foundation/Slab | 7/2/2024 | Corrections Issued | MICHAEL LEWIS |
| Underground Mechanical | 7/2/2024 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 7/3/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 8/1/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 8/1/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 8/1/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/1/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Rough-Elec/Plmb/HVAC | 8/5/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 8/8/2024 | Conditional Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 8/14/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/14/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 11/22/2024 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 11/22/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 11/22/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 12/2/2024 | Conditional Approval | SABAS ALONSO |
| Green Building Rough | 12/2/2024 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 12/6/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 12/6/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 12/6/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 12/12/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 12/12/2024 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 12/17/2024 | Approved | JOSE MACIAS |
| Final | 2/21/2025 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 2/21/2025 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 2/21/2025 | SGSOV Not Required | JOSE MACIAS |
| Service/Power Release | 2/21/2025 | Not Ready for Inspection | JOSE MACIAS |
| Smoke Detectors | 2/21/2025 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 3/10/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 3/10/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 3/10/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/10/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 3/10/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 4/18/2025 | Not Ready for Inspection | MICHAEL LEWIS |
| Service/Power Release | 4/18/2025 | Not Ready for Inspection | MICHAEL LEWIS |
| Final | 4/28/2025 | No Access for Inspection | MICHAEL LEWIS |
| Service/Power Release | 4/28/2025 | No Access for Inspection | MICHAEL LEWIS |
| ELECTRICAL-Final | 4/29/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 4/29/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 4/29/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 4/29/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 6/20/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Service/Power Release | 6/20/2025 | Not Ready for Inspection | WAYNE REGESTER |