112 W 60TH ST 90003

Certificate Information: 112 W 60TH ST 90003

Application / Permit
23010-20000-04762
Plan Check / Job No.
B23VN16227
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
Permit Issued
Issued on 4/5/2024
Issuing Office
Current Status
Issued on 4/5/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/1/2023 APPLICANT
Assigned to Plan Check Engineer 12/6/2023 PINANK PATEL
Corrections Issued 12/13/2023 PINANK PATEL
Plan Check Approved 1/24/2024 ROSENDO MEDINA
Issued 4/5/2024 APPLICANT

Permit Application Clearance Information

Hold Cleared 12/13/2023 MARIA VENDIVIL
Address approval Cleared 12/22/2023 TREVOR QUAN
CPC Cleared 12/22/2023 ASHLEY RODARTE
Eng Process Fee Ord 176,300 Cleared 12/26/2023 TREVOR QUAN
Sewer availability Cleared 12/26/2023 TREVOR QUAN
Low Impact Development (LID) Cleared 1/2/2024 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 1/6/2024 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 1/26/2024 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/16/2024 Corrections Issued ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 7/2/2024 Partial Approval MICHAEL LEWIS
Footing/Foundation/Slab 7/2/2024 Corrections Issued MICHAEL LEWIS
Underground Mechanical 7/2/2024 Approved MICHAEL LEWIS
Footing/Foundation/Slab 7/3/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 8/1/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 8/1/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 8/1/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 8/1/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 8/5/2024 Corrections Issued ALEJANDRO DE ARTOLA
Rough-Elec/Plmb/HVAC 8/5/2024 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Wood Construction 8/8/2024 Conditional Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 8/14/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 8/14/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 8/14/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 11/22/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 11/22/2024 Approved MICHAEL LEWIS
PLUMBING-Rough 11/22/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 12/2/2024 Conditional Approval SABAS ALONSO
Green Building Rough 12/2/2024 Approved SABAS ALONSO
BUILDING-Rough-Frame 12/6/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 12/6/2024 Approved ALEJANDRO DE ARTOLA
Insulation 12/6/2024 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/12/2024 Approved ALEJANDRO DE ARTOLA
Insulation 12/12/2024 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 12/17/2024 Approved JOSE MACIAS
Final 2/21/2025 Corrections Issued JOSE MACIAS
Green Building Final 2/21/2025 Approved JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 2/21/2025 SGSOV Not Required JOSE MACIAS
Service/Power Release 2/21/2025 Not Ready for Inspection JOSE MACIAS
Smoke Detectors 2/21/2025 Approved JOSE MACIAS
ELECTRICAL-Final 3/10/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 3/10/2025 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 3/10/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 3/10/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 3/10/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 4/18/2025 Not Ready for Inspection MICHAEL LEWIS
Service/Power Release 4/18/2025 Not Ready for Inspection MICHAEL LEWIS
Final 4/28/2025 No Access for Inspection MICHAEL LEWIS
Service/Power Release 4/28/2025 No Access for Inspection MICHAEL LEWIS
ELECTRICAL-Final 4/29/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 4/29/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 4/29/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 4/29/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 6/20/2025 Not Ready for Inspection WAYNE REGESTER
Service/Power Release 6/20/2025 Not Ready for Inspection WAYNE REGESTER