4934 N STROHM AVE 91601

Certificate Information: 4934 N STROHM AVE 91601

Application / Permit
23010-20000-04721
Plan Check / Job No.
B23VN16118
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 1-STORY ACCESSORY DWELLING UNIT (18'-6"x19'-0"), 315 SQFT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g). ALL ELECTRIC BUILDING
Permit Issued
Issued on 3/12/2024
Issuing Office
Valley
Current Status
CofO Issued on 9/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2023 APPLICANT
Assigned to Plan Check Engineer 11/30/2023 PETER MOSESIAN
Corrections Issued 12/8/2023 PETER MOSESIAN
Quality Review Completed 12/8/2023 OMID HEDAYAT
Building Plans Picked Up 12/11/2023 APPLICANT
Plan Check Approved 2/27/2024 PETER MOSESIAN
Issued 3/12/2024 APPLICANT
CofO in Progress 9/4/2025 ROBERTO PALACIOS-LOPEZ
Permit Finaled 9/11/2025 RUBEN SALAS
CofO Issued 9/11/2025 RUBEN SALAS
Permit Finaled 9/11/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/19/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 12/20/2023 NIKKI ZULUETA
Sewer availability Cleared 12/22/2023 NIKKI ZULUETA
Construction near power lines Cleared 1/16/2024 WALTER RAMIREZ
Low Impact Development (LID) Cleared 1/19/2024 MELINEH AGHAKHABIAN
Hydrant and Access approval Cleared 1/29/2024 KURT CORRAL
Roof/Waste drainage to street Cleared 2/23/2024 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423
Landscape Architect Alaniz,, Arthur Louis; Lic. No.: LA5554 26 CLEAR VISTA      ROLLING HILLS ESTATES, CA 90274

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/8/2024 Partial Approval JOHN HAYES
Special/Order Compliance 4/8/2024 Approved JOHN HAYES
Underground Mechanical 4/8/2024 Approved JOHN HAYES
Excavation/Setback/Form/Re-Bar 4/22/2024 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 4/22/2024 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 4/26/2024 No Access for Inspection JOHN COLEMAN
Excavation/Setback/Form/Re-Bar 4/29/2024 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 5/1/2024 Partial Inspection JOHN COLEMAN
Excavation/Setback/Form/Re-Bar 5/3/2024 Approved JOHN COLEMAN
Structural Steel Frame 6/26/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Wood Frame 6/26/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 7/8/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 7/12/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 7/12/2024 Approved ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 7/12/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 8/6/2024 Conditional Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 8/6/2024 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 8/6/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 8/6/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Rough 8/6/2024 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 8/6/2024 Approved ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 8/6/2024 Approved ROBERTO PALACIOS-LOPEZ
Wood Frame 8/6/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 9/13/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Insulation 10/16/2024 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 10/16/2024 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 10/24/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Rough 10/24/2024 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 10/24/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Drywall Nailing 10/30/2024 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 11/20/2024 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 4/29/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 4/29/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 4/29/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 4/29/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Final 4/29/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 4/29/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 4/29/2025 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 4/29/2025 SGSOV Not Required ROBERTO PALACIOS-LOPEZ
Service/Power Release 4/29/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 4/29/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 5/9/2025 No Access for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Final 5/9/2025 No Access for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 5/14/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Final 5/14/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 7/11/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 7/11/2025 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 7/11/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 8/29/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Service/Power Release 8/29/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 9/4/2025 OK to Issue CofO ROBERTO PALACIOS-LOPEZ