14757 W KITTRIDGE ST 91405

Certificate Information: 14757 W KITTRIDGE ST 91405

Application / Permit
23010-20000-04716
Plan Check / Job No.
B23VN16104
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Proposed new irregular shaped 49' x 30' 10" single family dwelling per SB9, NFPA 13D sprinkler is required. All work done per engineer.
Permit Issued
Issued on 1/25/2024
Issuing Office
Current Status
CofO Issued on 10/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2023 APPLICANT
Assigned to Plan Check Engineer 11/30/2023 NAREG ATARIAN
Corrections Issued 12/2/2023 NAREG ATARIAN
Quality Review Completed 12/4/2023 OMID HEDAYAT
Building Plans Picked Up 12/7/2023 APPLICANT
Plan Check Approved 1/25/2024 NAREG ATARIAN
Issued 1/25/2024 APPLICANT
CofO in Progress 9/30/2024 RYAN SALAZAR
CofO Issued 10/1/2024 DANIEL ORRANTE
Permit Finaled 10/1/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/5/2023 CARLOS RAMIREZ
Senate Bill 9 Cleared 12/12/2023 BRENNEN OBETO
Eng Process Fee Ord 176,300 Cleared 12/14/2023 CARLOS RAMIREZ
Sewer availability Cleared 12/14/2023 CARLOS RAMIREZ
Low Impact Development (LID) Cleared 1/9/2024 LUIS CRUZ
Roof/Waste drainage to street Cleared 1/16/2024 CARLOS RAMIREZ
Hydrant and Access approval Cleared 1/24/2024 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/13/2024 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 2/21/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 3/8/2024 Not Ready for Inspection RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 3/8/2024 Approved RYAN SALAZAR
Green Building Rough 3/8/2024 Not Ready for Inspection RYAN SALAZAR
Verify Sprinkler Sign Off 3/8/2024 Not Ready for Inspection RYAN SALAZAR
ELECTRICAL-Rough 4/4/2024 Approved RYAN SALAZAR
HVAC-Rough 4/4/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 4/4/2024 Partial Approval RYAN SALAZAR
PLUMBING-Rough 4/4/2024 Approved RYAN SALAZAR
Shower Pan 4/4/2024 Approved RYAN SALAZAR
Insulation 5/15/2024 Approved RYAN SALAZAR
Drywall Nailing 5/17/2024 Approved RYAN SALAZAR
Green Building Rough 5/17/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 8/12/2024 Approved RYAN SALAZAR
Final 8/12/2024 Partial Approval RYAN SALAZAR
Green Building Final 8/12/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 8/12/2024 SGSOV Approved RYAN SALAZAR
Service/Power Release 8/12/2024 Approved RYAN SALAZAR
Smoke Detectors 8/12/2024 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 8/12/2024 Approved RYAN SALAZAR
Final 10/1/2024 OK to Issue CofO RYAN SALAZAR