1641 1/2 S POINT VIEW ST 90035

Certificate Information: 1641 1/2 S POINT VIEW ST 90035

Application / Permit
23010-20000-04712
Plan Check / Job No.
B23VN16095
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING GARAGE WITH ADDITION INTO A 1-STORY (28'-3" X 19' IRREGULAR SHAPE) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) - (d). NFPA 13D FIRE SPRINKLERS THROUGHOUT.
Permit Issued
Issued on 12/4/2024
Issuing Office
Valley
Current Status
CofO Issued on 2/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2023 APPLICANT
Assigned to Plan Check Engineer 12/7/2023 VAHAN JIVALAGIAN
Corrections Issued 12/9/2023 VAHAN JIVALAGIAN
Quality Review Completed 12/13/2023 OMID HEDAYAT
Building Plans Picked Up 2/13/2024 APPLICANT
Applicant returned to address corrections 8/20/2024 VAHAN JIVALAGIAN
Applicant returned to address corrections 11/26/2024 VAHAN JIVALAGIAN
Plan Check Approved 12/4/2024 VAHAN JIVALAGIAN
Issued 12/4/2024 APPLICANT
CofO in Progress 2/11/2026 BRENDAN MORELLI
Permit Finaled 2/13/2026 DEROLD HAUFF
CofO Issued 2/13/2026 DEROLD HAUFF
Permit Finaled 2/13/2026 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development (LID) Cleared 6/13/2024 LUIS LUVANO
Address approval Cleared 6/17/2024 WALLIE JONG
Hydrant and Access approval Cleared 11/5/2024 JERRY KAO
Roof/Waste drainage to street Cleared 11/15/2024 JEANIE LAM
Sewer availability Cleared 11/15/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 11/27/2024 CHRISTINA BRACO

Contact Information

Contractor Owner-Builder       ,
Engineer Nazari,, Arthur; Lic. No.: C53497 PO BOX 7112      NORTHRIDGE, CA 91327

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/14/2025 Approved ARTHUR NEGRETE
Excavation/Setback/Form/Re-Bar 1/15/2025 Approved ARTHUR NEGRETE
Footing/Foundation/Slab 1/15/2025 Approved ARTHUR NEGRETE
METHANE-Barrier 1/15/2025 Approved ARTHUR NEGRETE
METHANE-Subgrade 1/15/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 6/5/2025 Approved ARTHUR NEGRETE
HVAC-Rough 6/6/2025 Approved ARTHUR NEGRETE
PLUMBING-Rough 6/6/2025 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 6/9/2025 Approved ARTHUR NEGRETE
Green Building Rough 6/9/2025 Approved ARTHUR NEGRETE
METHANE-Rough 6/9/2025 Approved ARTHUR NEGRETE
Wood Frame 6/9/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 7/14/2025 Approved ARTHUR NEGRETE
Insulation 7/18/2025 Approved ANTHONY RAMOS
Drywall Nailing 7/29/2025 Approved DEVON JACKSON
Interior/Exterior Lathing 8/6/2025 Approved DEVON JACKSON
ELECTRICAL-Final 12/3/2025 Corrections Issued BRENDAN MORELLI
HVAC-Final 12/3/2025 Corrections Issued BRENDAN MORELLI
PLUMBING-Final 12/3/2025 Approved BRENDAN MORELLI
ELECTRICAL-Final 2/10/2026 Approved BRENDAN MORELLI
Final 2/10/2026 OK to Issue CofO BRENDAN MORELLI
Green Building Final 2/10/2026 Approved BRENDAN MORELLI
HVAC-Final 2/10/2026 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 2/10/2026 SGSOV Approved BRENDAN MORELLI
Smoke Detectors 2/10/2026 Approved BRENDAN MORELLI