10603 W ROCHESTER AVE 90024
Certificate Information: 10603 W ROCHESTER AVE 90024
- Application / Permit
- 23010-20000-04711
- Plan Check / Job No.
- B23VN16090
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY (86' X 66'-2" IRREGULAR SHAPE) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND TRELLIS PATIO COVER. NFPA 13D FIRE SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 1/30/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 1/30/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2023 | VAHAN JIVALAGIAN |
| Corrections Issued | 12/7/2023 | VAHAN JIVALAGIAN |
| Quality Review Completed | 12/12/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 12/12/2023 | APPLICANT |
| Applicant returned to address corrections | 1/9/2024 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 5/20/2024 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 6/17/2024 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 8/20/2024 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 11/19/2024 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 12/26/2024 | VAHAN JIVALAGIAN |
| Plan Check Approved | 1/16/2025 | OMID HEDAYAT |
| Issued | 1/30/2025 | APPLICANT |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 12/5/2023 | VAHAN JIVALAGIAN |
| Grading Pre-Inspection | Cleared | 12/5/2023 | VAHAN JIVALAGIAN |
| Address approval | Cleared | 2/15/2024 | ANDREA SAINT-ANTONIN |
| Sewer availability | Cleared | 2/15/2024 | ANDREA SAINT-ANTONIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2024 | ANDREA SAINT-ANTONIN |
| Construction near power lines | Cleared | 4/20/2024 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 5/25/2024 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 5/30/2024 | AMMAR ELTAWIL |
| Specific Plan | Cleared | 7/11/2024 | JOSHUA JONES |
| Roof/Waste drainage to street | Cleared | 7/16/2024 | KIMBERLY HERNANDEZ |
Contact Information
| Contractor | Delta West Construction; Lic. No.: 794816-B | 132 S LA PEER DR BEVERLY HILLS, CA 90211 |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | PO BOX 7112 NORTHRIDGE, CA 91327 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Insulation | 7/22/2026 Time Frame: 9-11 |
Inspection Request History
| Sewer | 2/3/2025 | Partial Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 7/18/2025 | Conditional Approval | KIRK SANDERS |
| METHANE-Barrier | 7/18/2025 | Not Ready for Inspection | KIRK SANDERS |
| METHANE-Subgrade | 7/18/2025 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Rough | 8/1/2025 | Partial Approval | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 8/6/2025 | Partial Approval | SEAN HAUPT |
| METHANE-Barrier | 8/6/2025 | Not Ready for Inspection | SEAN HAUPT |
| METHANE-Subgrade | 8/6/2025 | Not Ready for Inspection | SEAN HAUPT |
| Footing/Foundation/Slab | 8/18/2025 | Conditional Approval | ARAM AVEDISIAN |
| METHANE-Subgrade | 8/18/2025 | Partial Approval | ARAM AVEDISIAN |
| METHANE-Subgrade | 8/22/2025 | Approved | ARAM AVEDISIAN |
| Deputy Methane Barrier | 8/27/2025 | Conditional Approval | MICHAEL PELHAM |
| Deputy Methane Barrier | 8/28/2025 | Conditional Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 9/3/2025 | Approved | ARAM AVEDISIAN |
| METHANE-Barrier | 9/3/2025 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2025 | Partial Approval | MICHAEL ALLEN |
| Deputy Steel/Welding | 11/14/2025 | Conditional Approval | ANDREW NAVE |
| Deputy Wood Construction | 11/26/2025 | Conditional Approval | ANDREW NAVE |
| Gas Test | 1/21/2026 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 1/21/2026 | Approved | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2026 | Partial Approval | MICHAEL ALLEN |
| Reinforced Concrete Frame | 2/18/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| ELECTRICAL-Rough | 3/31/2026 | Conditional Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 4/20/2026 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Rough | 4/20/2026 | Corrections Issued | CARLOS MATAMOROS |
| METHANE-Rough | 4/20/2026 | Not Ready for Inspection | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 4/20/2026 | Approved | CARLOS MATAMOROS |
| Shower Pan | 6/25/2026 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 6/29/2026 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 6/29/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/29/2026 | Not Ready for Inspection | ANTHONY EGSON |
| METHANE-Rough | 6/29/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 7/8/2026 | Partial Approval | ANTHONY EGSON |
| METHANE-Rough | 7/14/2026 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 7/15/2026 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2026 | Approved | ANTHONY EGSON |
| Green Building Rough | 7/15/2026 | Approved | ANTHONY EGSON |
| Deputy Wood Construction | 7/16/2026 | Conditional Approval | ANTHONY EGSON |