5728 N CALVIN AVE 91356
Certificate Information: 5728 N CALVIN AVE 91356
- Application / Permit
- 23010-20000-04672
- Plan Check / Job No.
- B23VN16003
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- NEW 55' X 26'-6" ONE STORY ACCESSORY LIVING QUARTERS; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 6/7/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/4/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2023 | SELLA BENYAMIN |
| Corrections Issued | 11/28/2023 | SELLA BENYAMIN |
| Quality Review Completed | 11/30/2023 | STEVEN KIM |
| Building Plans Picked Up | 12/4/2023 | APPLICANT |
| Plan Check Approved | 3/5/2024 | SELLA BENYAMIN |
| Issued | 6/7/2024 | APPLICANT |
| CofO in Progress | 3/31/2026 | SEAN WIRCH |
| Permit Finaled | 4/4/2026 | MICHAEL PELHAM |
| CofO Issued | 4/4/2026 | MICHAEL PELHAM |
| Permit Finaled | 4/4/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 1/23/2024 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 1/29/2024 | COLIN LOREDO |
| Sewer availability | Cleared | 2/23/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2024 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | 23300 POMPANO STREET MALIBU, CA 90265 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/26/2024 | Conditional Approval | JON MCHUGH |
| Footing/Foundation/Slab | 7/3/2024 | Not Ready for Inspection | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 7/10/2024 | Partial Approval | JON MCHUGH |
| Footing/Foundation/Slab | 7/10/2024 | Corrections Issued | JON MCHUGH |
| Special/Order Compliance | 7/10/2024 | Partial Inspection | SEAN WIRCH |
| Footing/Foundation/Slab | 10/21/2024 | Approved | JON MCHUGH |
| Special/Order Compliance | 10/21/2024 | Corrections Issued | JON MCHUGH |
| Deputy Drilled-In Anchors | 11/1/2024 | Conditional Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2024 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2024 | Partial Approval | JON MCHUGH |
| Wood Frame | 11/18/2024 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 12/2/2024 | Partial Approval | JON MCHUGH |
| HVAC-Rough | 1/3/2025 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 1/13/2025 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 1/24/2025 | Approved | JON MCHUGH |
| Green Building Rough | 1/24/2025 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 1/24/2025 | Partial Approval | JON MCHUGH |
| MERV13>=Rough | 1/24/2025 | Approved | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 1/24/2025 | Approved | JON MCHUGH |
| Verify Sprinkler Sign Off | 1/24/2025 | Approved | JON MCHUGH |
| Insulation | 2/3/2025 | Approved | JON MCHUGH |
| Shower Pan | 2/3/2025 | Not Ready for Inspection | JON MCHUGH |
| Drywall Nailing | 2/11/2025 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 3/11/2025 | Approved | JON MCHUGH |
| Shower Pan | 3/11/2025 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 3/24/2025 | Approved | JON MCHUGH |
| Shower Pan | 3/24/2025 | Approved | JON MCHUGH |
| Final | 4/2/2026 | OK to Issue CofO | SEAN WIRCH |
| Green Building Final | 4/2/2026 | Approved | SEAN WIRCH |
| MERV13>=Final | 4/2/2026 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 4/2/2026 | SGSOV Approved | SEAN WIRCH |
| Service/Power Release | 4/2/2026 | Approved | SEAN WIRCH |
| Smoke Detectors | 4/2/2026 | Approved | SEAN WIRCH |