17248 W PARTHENIA ST 91325
Certificate Information: 17248 W PARTHENIA ST 91325
- Application / Permit
- 23010-20000-04662
- Plan Check / Job No.
- B23VN15985
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 27'-10" X 53'-5" IRREGULAR SHAPED DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). FIRE SPRINKLER REQUIRED THROUGHOUT.
- Permit Issued
- Issued on 10/3/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/27/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 11/27/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 11/29/2023 | APPLICANT |
| Plan Check Approved | 3/22/2024 | KAMYAR EMAMI |
| Issued | 10/3/2024 | APPLICANT |
| CofO in Progress | 12/30/2025 | JOAQUIN GREENOUGH |
| Permit Finaled | 12/31/2025 | RUBEN SALAS |
| CofO Issued | 12/31/2025 | RUBEN SALAS |
| Permit Finaled | 12/31/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/3/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 2/8/2024 | EDGAR ALCARAZ |
| Low Impact Development (LID) | Cleared | 2/26/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 3/4/2024 | EDGAR ALCARAZ |
| Hydrant and Access approval | Cleared | 3/20/2024 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Papazyan,, Andranik; Lic. No.: C56824 | 635 W COLORADO ST STE 104 GLENDALE, CA 91204 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/21/2024 | Partial Approval | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 10/25/2024 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 10/25/2024 | Approved | MATTHEW NELSON |
| Wood Frame | 5/7/2025 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/13/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 6/10/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 6/10/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 6/10/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 6/16/2025 | Approved | NICHOLAS TROWBRIDGE |
| Wood Frame | 7/24/2025 | No Access for Inspection | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 7/28/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 7/28/2025 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 7/28/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 7/28/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 7/28/2025 | Approved | NICHOLAS TROWBRIDGE |
| Insulation | 8/7/2025 | Approved | JOSE AVILA |
| Drywall Nailing | 8/15/2025 | Approved | NICHOLAS TROWBRIDGE |
| Shower Pan | 8/25/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 9/12/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 9/16/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 11/7/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Final | 11/7/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 11/7/2025 | SGSOV Not Required | NICHOLAS TROWBRIDGE |
| Service/Power Release | 11/7/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 11/7/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 11/18/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Final | 11/18/2025 | Approved | NICHOLAS TROWBRIDGE |
| Service/Power Release | 11/18/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Final | 11/20/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Service/Power Release | 11/20/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 12/30/2025 | OK to Issue CofO | JOAQUIN GREENOUGH |
| Final | 12/30/2025 | Partial Inspection | CHRISTOPHER ROJAS |