17127 N HART PL 91406
Certificate Information: 17127 N HART PL 91406
- Application / Permit
- 23010-20000-04645
- Plan Check / Job No.
- B23VN15953
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: NEW 2-STORY DETACHED 20'-0" x 30'-0" ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33 (c)-(d) WITH ATTACHED 20'-0" x 5'-6" PATIO COVER PER DESIGN
- Permit Issued
- Issued on 1/11/2025
- Issuing Office
- Current Status
- Issued on 1/11/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2024 | ALFRED RAMIREZ |
| Corrections Issued | 8/3/2024 | ALFRED RAMIREZ |
| Quality Review Completed | 8/6/2024 | STEVEN KIM |
| Applicant returned to address corrections | 11/15/2024 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 11/25/2024 | ALFRED RAMIREZ |
| Plan Check Approved | 12/3/2024 | ALFRED RAMIREZ |
| No Progress | 12/19/2024 | ALFRED RAMIREZ |
| Plan Check Approved | 12/19/2024 | ALFRED RAMIREZ |
| Issued | 1/11/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/15/2024 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 11/15/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/19/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 11/19/2024 | RYAN CASTRO |
Contact Information
| Architect | Svalbe,, John W; Lic. No.: C33344 | 1830 AMARGOSA DRIVE PALMDALE, CA 93551 |
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 2/28/2025 | Corrections Issued | JON MCHUGH |
| Underground Mechanical | 2/28/2025 | Conditional Approval | JON MCHUGH |
| Footing/Foundation/Slab | 3/25/2025 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 4/1/2025 | Approved | JON MCHUGH |
| Special/Order Compliance | 4/1/2025 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2025 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2025 | Corrections Issued | JON MCHUGH |
| BUILDING-Rough-Frame | 7/7/2025 | Corrections Issued | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2025 | Partial Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 8/5/2025 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 8/5/2025 | Corrections Issued | JON MCHUGH |
| HVAC-Rough | 8/5/2025 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 8/5/2025 | Not Ready for Inspection | JON MCHUGH |
| Verify Sprinkler Sign Off | 8/5/2025 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 8/18/2025 | Partial Approval | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2025 | Corrections Issued | MORRIS JACKSON |
| PLUMBING-Rough | 8/18/2025 | Approved | MORRIS JACKSON |
| Deputy Wood Construction | 8/20/2025 | Partial Approval | SEAN WIRCH |
| ELECTRICAL-Rough | 8/20/2025 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2025 | Partial Approval | JON MCHUGH |
| HVAC-Rough | 8/20/2025 | Approved | JON MCHUGH |
| PLUMBING-Rough | 8/20/2025 | Approved | JON MCHUGH |
| Wood Frame | 8/20/2025 | Corrections Issued | JON MCHUGH |
| Insulation | 8/27/2025 | Conditional Approval | JON MCHUGH |
| Interior/Exterior Lathing | 8/27/2025 | Partial Approval | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 8/27/2025 | Approved | JON MCHUGH |
| Drywall Nailing | 9/9/2025 | Corrections Issued | SCOTT SOBEL |
| Shower Pan | 9/26/2025 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 10/9/2025 | Approved | JON MCHUGH |
| Underground Mechanical | 11/13/2025 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 12/12/2025 | Not Ready for Inspection | JON MCHUGH |
| Drywall Nailing | 12/12/2025 | Approved | JON MCHUGH |
| Final | 12/12/2025 | Corrections Issued | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 12/12/2025 | SGSOV Approved | JON MCHUGH |
| Service/Power Release | 12/12/2025 | Not Ready for Inspection | JON MCHUGH |
| Smoke Detectors | 12/12/2025 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 12/17/2025 | Corrections Issued | JON MCHUGH |
| PLUMBING-Final | 12/17/2025 | Approved | JON MCHUGH |