15013 W MARLIN PL 91405

Certificate Information: 15013 W MARLIN PL 91405

Application / Permit
23010-20000-04637
Plan Check / Job No.
B23VN15921
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 1-story detached ADU per LAMC 12.22 A.33 (c)-(d), work per WFPP
Permit Issued
Issued on 3/7/2024
Issuing Office
Valley
Current Status
CofO Issued on 8/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/17/2023 APPLICANT
Assigned to Plan Check Engineer 11/22/2023 RAMA DABADGE
Corrections Issued 11/27/2023 RAMA DABADGE
Building Plans Picked Up 12/22/2023 APPLICANT
Applicant returned to address corrections 3/1/2024 ANGELICA DAVE
Plan Check Approved 3/5/2024 ARAMIK SHAHMIRZAIAN
Issued 3/7/2024 APPLICANT
CofO in Progress 8/5/2024 RYAN SALAZAR
CofO Issued 8/19/2024 DANIEL ORRANTE
Permit Finaled 8/19/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/22/2023 RYAN KIM
Eng Process Fee Ord 176,300 Cleared 12/26/2023 LEE GUILBEAUX
Sewer availability Cleared 12/27/2023 RYAN KIM
Low Impact Development (LID) Cleared 1/4/2024 TOMMY YIN
Roof/Waste drainage to street Cleared 1/5/2024 RYAN KIM
Hydrant and Access approval Cleared 2/10/2024 GILBERT URREA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/4/2024 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 4/10/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 4/19/2024 Approved RYAN SALAZAR
Pre-Inspection 4/19/2024 Partial Inspection RYAN SALAZAR
PLUMBING-Rough 4/24/2024 Approved JOHN COLEMAN
ELECTRICAL-Rough 4/26/2024 Partial Inspection RYAN SALAZAR
BUILDING-Rough-Frame 5/1/2024 Approved RYAN SALAZAR
ELECTRICAL-Rough 5/1/2024 Approved RYAN SALAZAR
Green Building Rough 5/1/2024 Approved RYAN SALAZAR
HVAC-Rough 5/1/2024 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 5/1/2024 Approved RYAN SALAZAR
Insulation 5/3/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 5/3/2024 Partial Approval RYAN SALAZAR
Drywall Nailing 5/8/2024 Approved RYAN SALAZAR
Shower Pan 5/8/2024 Approved RYAN SALAZAR
Shower Pan 5/13/2024 Approved LEONARD ROSS II
ELECTRICAL-Rough 6/14/2024 Approved RYAN SALAZAR
Final 7/15/2024 Corrections Issued RYAN SALAZAR
Green Building Final 7/15/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 7/15/2024 SGSOV Approved RYAN SALAZAR
Service/Power Release 7/15/2024 Approved RYAN SALAZAR
Smoke Detectors 7/15/2024 Approved RYAN SALAZAR
Final 8/5/2024 OK to Issue CofO RYAN SALAZAR