6208 N BEEMAN AVE 91606

Certificate Information: 6208 N BEEMAN AVE 91606

Application / Permit
23010-20000-04631
Plan Check / Job No.
B23VN15890
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 20' X 42' ONE STORY SINGLE FAMILY DWELLING PER SB9 ALL WORK PER WFPP NFPA 13D REQUIRED THROUGHOUT
Permit Issued
Issued on 1/16/2024
Issuing Office
Current Status
CofO Issued on 1/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/17/2023 APPLICANT
Assigned to Plan Check Engineer 11/21/2023 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 11/28/2023 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 11/28/2023 STEVEN KIM
Building Plans Picked Up 11/28/2023 APPLICANT
Plan Check Approved 1/8/2024 SEWADA ZADOORAN MILAGARDI
Issued 1/16/2024 APPLICANT
CofO in Progress 1/16/2026 OGANES TARAKHCHYAN
Permit Finaled 1/28/2026 RUBEN SALAS
CofO Issued 1/28/2026 RUBEN SALAS
Permit Finaled 1/28/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/28/2023 GABRIELLA TORRES
Eng Process Fee Ord 176,300 Cleared 11/29/2023 GABRIELLA TORRES
Sewer availability Cleared 11/29/2023 GABRIELLA TORRES
Senate Bill 9 Cleared 12/7/2023 NELSON RODRIGUEZ
Hydrant and Access approval Cleared 12/8/2023 LAVEON RIDER
Low Impact Development (LID) Cleared 1/3/2024 TRISH PARAS
Roof/Waste drainage to street Cleared 1/3/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/9/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 7/9/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Sewer 7/9/2024 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 7/9/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Underground Mechanical 8/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 8/20/2024 Partial Approval SALVADOR MARTINEZ
PLUMBING-Rough 8/20/2024 Partial Approval SALVADOR MARTINEZ
Special/Order Compliance 8/20/2024 Corrections Issued SALVADOR MARTINEZ
Underground Mechanical 8/20/2024 Not Ready for Inspection SALVADOR MARTINEZ
Footing/Foundation/Slab 8/28/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 10/22/2024 Not Ready for Inspection GAREN HAYRAPETYAN
ELECTRICAL-Rough 10/22/2024 Approved GAREN HAYRAPETYAN
Green Building Rough 10/22/2024 Not Ready for Inspection GAREN HAYRAPETYAN
HVAC-Rough 10/22/2024 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 10/22/2024 Corrections Issued GAREN HAYRAPETYAN
Verify Sprinkler Sign Off 10/22/2024 Corrections Issued GAREN HAYRAPETYAN
PLUMBING-Rough 11/5/2024 Corrections Issued OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 11/5/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 11/8/2024 Not Ready for Inspection GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 11/8/2024 Approved GAREN HAYRAPETYAN
Green Building Rough 11/8/2024 Not Ready for Inspection GAREN HAYRAPETYAN
PLUMBING-Rough 11/13/2024 Approved OGANES TARAKHCHYAN
Wood Frame 11/13/2024 Approved OGANES TARAKHCHYAN
Insulation 11/21/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 11/21/2024 Partial Approval OGANES TARAKHCHYAN
Shower Pan 11/21/2024 Approved OGANES TARAKHCHYAN
Drywall Nailing 11/27/2024 Approved MICHAEL CORTEZ
Green Building Rough 11/27/2024 Approved MICHAEL CORTEZ
BUILDING-Rough-Frame 10/16/2025 Approved OGANES TARAKHCHYAN
Final 10/16/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 10/16/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Service/Power Release 10/16/2025 Approved OGANES TARAKHCHYAN
Smoke Detectors 10/16/2025 Approved OGANES TARAKHCHYAN
Final 1/15/2026 OK to Issue CofO OGANES TARAKHCHYAN
Green Building Final 1/15/2026 Approved OGANES TARAKHCHYAN
Service/Power Release 1/15/2026 Approved OGANES TARAKHCHYAN