6208 N BEEMAN AVE 91606
Certificate Information: 6208 N BEEMAN AVE 91606
- Application / Permit
- 23010-20000-04631
- Plan Check / Job No.
- B23VN15890
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 20' X 42' ONE STORY SINGLE FAMILY DWELLING PER SB9 ALL WORK PER WFPP NFPA 13D REQUIRED THROUGHOUT
- Permit Issued
- Issued on 1/16/2024
- Issuing Office
- Current Status
- CofO Issued on 1/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2023 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 11/28/2023 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 11/28/2023 | STEVEN KIM |
| Building Plans Picked Up | 11/28/2023 | APPLICANT |
| Plan Check Approved | 1/8/2024 | SEWADA ZADOORAN MILAGARDI |
| Issued | 1/16/2024 | APPLICANT |
| CofO in Progress | 1/16/2026 | OGANES TARAKHCHYAN |
| Permit Finaled | 1/28/2026 | RUBEN SALAS |
| CofO Issued | 1/28/2026 | RUBEN SALAS |
| Permit Finaled | 1/28/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/28/2023 | GABRIELLA TORRES |
| Eng Process Fee Ord 176,300 | Cleared | 11/29/2023 | GABRIELLA TORRES |
| Sewer availability | Cleared | 11/29/2023 | GABRIELLA TORRES |
| Senate Bill 9 | Cleared | 12/7/2023 | NELSON RODRIGUEZ |
| Hydrant and Access approval | Cleared | 12/8/2023 | LAVEON RIDER |
| Low Impact Development (LID) | Cleared | 1/3/2024 | TRISH PARAS |
| Roof/Waste drainage to street | Cleared | 1/3/2024 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/9/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 7/9/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Sewer | 7/9/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 7/9/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 8/15/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 8/20/2024 | Partial Approval | SALVADOR MARTINEZ |
| PLUMBING-Rough | 8/20/2024 | Partial Approval | SALVADOR MARTINEZ |
| Special/Order Compliance | 8/20/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Underground Mechanical | 8/20/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 8/28/2024 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 10/22/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 10/22/2024 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 10/22/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| HVAC-Rough | 10/22/2024 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 10/22/2024 | Corrections Issued | GAREN HAYRAPETYAN |
| Verify Sprinkler Sign Off | 10/22/2024 | Corrections Issued | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 11/5/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 11/5/2024 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 11/8/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2024 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 11/8/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 11/13/2024 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 11/13/2024 | Approved | OGANES TARAKHCHYAN |
| Insulation | 11/21/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 11/21/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Shower Pan | 11/21/2024 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 11/27/2024 | Approved | MICHAEL CORTEZ |
| Green Building Rough | 11/27/2024 | Approved | MICHAEL CORTEZ |
| BUILDING-Rough-Frame | 10/16/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 10/16/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 10/16/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Service/Power Release | 10/16/2025 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 10/16/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 1/15/2026 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Green Building Final | 1/15/2026 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 1/15/2026 | Approved | OGANES TARAKHCHYAN |